* Type B Past Week Summary * Flags and metal prisms ordered; expected 5/31. * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws): * Crane adapter * Lower breadboard blade module (with cable clamps) * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete) * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram) * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]]) * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]]) * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro. * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later). * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]]) |
* Hirata-san: * Made cables for LVDT. * Made drawings for new wire clamps. * Asked ATC for manufacturing parts.(and modified drawings.) * Asked quotes for SDC coating for hooks. * Sent packing tools for BF. * Talked with i-ject about quotes for payload. * Mark and Fabian at Kamioka (plus Enzo for 2 days): * Finished rebalance of IM * Reinstalled IRM, adjusted OSEMs * Replaced broken Type 3 cable on IM-H1 OSEM. * Fixed issues with k1visbs real-time model. * Started TFs from IRM OSEMs to IRM and IM OSEMs. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Hirata-san:
- Made cables for LVDT.
- Made drawings for new wire clamps.
- Asked ATC for manufacturing parts.(and modified drawings.)
- Asked quotes for SDC coating for hooks.
- Sent packing tools for BF.
- Talked with i-ject about quotes for payload.
- Mark and Fabian at Kamioka (plus Enzo for 2 days):
- Finished rebalance of IM
- Reinstalled IRM, adjusted OSEMs
- Replaced broken Type 3 cable on IM-H1 OSEM.
- Fixed issues with k1visbs real-time model.
- Started TFs from IRM OSEMs to IRM and IM OSEMs.