 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]])
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
 * We removed the BF cap to debug the stepper motor. We checked the cabling but didn't find a problem. Eventually toggling the power to the driver box seemed to fix it.
 * We got the wheels removed from the two tall stepladders.
 * We started to rebalance the IM but came to realize that it was unstable for more than trivial pitch and roll (and had been for some time). We moved trim mass from top to bottom and it became unconditionally stable.
 * We rebalance the IM, put back the IRM and adjusted the OSEMs.
 * We took a successful TF in IM-L.
 * We added the security structure ring for below the SF and then added the SF. We noticed the cap is on at the wrong angle (so the keystone lock screws are inaccessible) but we can easily fix that.
 
==== Plan for coming weeks ====
Next week:
 * Everyone (Mark, Fabian, Enzo, Perry Hirata-san) at Kamioka, Monday-Friday except for Hirata-san Wednesday-Friday).
 * Finish SF installation.
 * Finish BF cabling, hang BF/IRM/IM/RM/BS from SF and confirm weight matches load capacity.
 * Re-trim BF as necessary.
 * Get picomotor driver working.
Week after next:
 * Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Friday.
 * Prepare for PI installation.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We removed the BF cap to debug the stepper motor. We checked the cabling but didn't find a problem. Eventually toggling the power to the driver box seemed to fix it.
  • We got the wheels removed from the two tall stepladders.
  • We started to rebalance the IM but came to realize that it was unstable for more than trivial pitch and roll (and had been for some time). We moved trim mass from top to bottom and it became unconditionally stable.
  • We rebalance the IM, put back the IRM and adjusted the OSEMs.
  • We took a successful TF in IM-L.
  • We added the security structure ring for below the SF and then added the SF. We noticed the cap is on at the wrong angle (so the keystone lock screws are inaccessible) but we can easily fix that.

Plan for coming weeks

Next week:

  • Everyone (Mark, Fabian, Enzo, Perry Hirata-san) at Kamioka, Monday-Friday except for Hirata-san Wednesday-Friday).
  • Finish SF installation.
  • Finish BF cabling, hang BF/IRM/IM/RM/BS from SF and confirm weight matches load capacity.
  • Re-trim BF as necessary.
  • Get picomotor driver working.

Week after next:

  • Everyone (Mark, Fabian, Enzo, Hirata-san) at Kamioka, Monday-Friday.
  • Prepare for PI installation.