* Type B Past Week Summary * Flags and metal prisms ordered; expected 5/31. * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws): * Crane adapter * Lower breadboard blade module (with cable clamps) * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete) * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram) * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]]) * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]]) * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro. * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later). * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Past week report ==== * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box. * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.) * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.) * Enzo found nearly all in-vacuum cables. * Enzo and Shoda-san got several more loops closed on the BS. * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4). * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them. * Hirata-san worked on SR procurement. * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank. ==== Plan for week of 12/4 ==== * Mark at Kamioka. * Fabian at f2f satellite meeting Mon, then Kamioka. * Enzo at f2f then Mitaka. * Hirata-san at Kamioka Mon-Thu, Mitaka Fri. * Kozu-kun Thu only. * Mirror gluing. * IM assembly and pico test. ==== Plan for week of 12/11 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka. * Kozu-kun Mon-Thu only. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
- Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
- Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
- Enzo found nearly all in-vacuum cables.
- Enzo and Shoda-san got several more loops closed on the BS.
- Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
- Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
- Hirata-san worked on SR procurement.
- Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
Plan for week of 12/4
- Mark at Kamioka.
- Fabian at f2f satellite meeting Mon, then Kamioka.
- Enzo at f2f then Mitaka.
- Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
- Kozu-kun Thu only.
- Mirror gluing.
- IM assembly and pico test.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
- Kozu-kun Mon-Thu only.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
- Enzo TBD, probably 12/22-1/3
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21