Differences between revisions 15 and 273 (spanning 258 versions)
Revision 15 as of 2016-05-13 09:43:08
Size: 1777
Editor: MarkBarton
Comment:
Revision 273 as of 2018-03-30 13:03:32
Size: 3231
Editor: EnzoTapia
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]])
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Report for week of 3/26 ====

BFs:

 * BF No. 1:
  * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
  * We wired the LVDT, Picomotor and Steppermotor.
  * We measured the keystone tilt at different points and the differences are within 0.1[mm]
  * We added cable clamps to the base.

 * BF No.7:
  * Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
  * The yoke position was corrected.
  * The fishing rod was assembled.
  * Compression tuning is ongoing.??

SFs:

 * Hirata-san and Tanioka-san set up the frame to check the SFs.

 * SF (B2-5):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly.
  * We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)

 * SF (B2-6):
  * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
  * We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)

SR3/SRM:

 * Kozu-kun and Enzo finished the SR3 in-air cabling.
 * Enzo prepared the SR3 and SRM rack in parallel (On going).


SR2:

 * Hirata-san tested the safety bars in the SR2 area.
 * We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.

BS:

 * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Shipping:

 * We received the LBB parts for SR2.
 * We received the Payload parts (IM and IRM) this morning.


==== Plan for week of 4/2 ====
 * Mark at Mitaka Mon, Kamioka from Tue.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * Finish BFs tasks (cabling +calibration)
 * Finish SFs tasks (cabling +calibration)
 * Add cable clamps to bases.
 * Add cable clamps and Cu segments to caps (only if they fit well).
 * Build 2xIM, 2xIRM
 * Glue SR3 mirror?

==== Plan for week of 4/9 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Finish IMs and IRMs
 * Build 1xRM
 * Glue SR3 mirror?

==== Plan for week of 4/16 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * Start SR3 Hang?

==== Plan for week of 4/23 ====
 * Shoda-san at Mitaka
 * Fujii-san at Mitaka?
 * Tanioka-san at Mitaka?
 * Others at Kamioka
 * --
 * F0 blade prototype test

==== Plan for week of 4/30 ====
  * Golden Week!

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 3/26

BFs:

  • BF No. 1:
    • Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
    • We wired the LVDT, Picomotor and Steppermotor.
    • We measured the keystone tilt at different points and the differences are within 0.1[mm]
    • We added cable clamps to the base.
  • BF No.7:
    • Tanioka-san and Fujii-san replaced the blades corresponding to the BS for the SR type blades.
    • The yoke position was corrected.
    • The fishing rod was assembled.
    • Compression tuning is ongoing.??

SFs:

  • Hirata-san and Tanioka-san set up the frame to check the SFs.
  • SF (B2-5):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. The cap didn't come out smoothly.
    • We measured the keystone tilt at different points, and the differences are within 0.1[mm] (65.5, 65.5, 65.5, 65.4)
  • SF (B2-6):
    • Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
    • We measured the keystone tilt at different points, and the differences are within 0.3[mm] (63.7, 63.5,63.8, 63.8)

SR3/SRM:

  • Kozu-kun and Enzo finished the SR3 in-air cabling.
  • Enzo prepared the SR3 and SRM rack in parallel (On going).

SR2:

  • Hirata-san tested the safety bars in the SR2 area.
  • We got new power supply for the SR2 Rack. Before, the power was coming from the BS rack.

BS:

  • Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).

Shipping:

  • We received the LBB parts for SR2.
  • We received the Payload parts (IM and IRM) this morning.

Plan for week of 4/2

  • Mark at Mitaka Mon, Kamioka from Tue.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • Finish BFs tasks (cabling +calibration)
  • Finish SFs tasks (cabling +calibration)
  • Add cable clamps to bases.
  • Add cable clamps and Cu segments to caps (only if they fit well).
  • Build 2xIM, 2xIRM
  • Glue SR3 mirror?

Plan for week of 4/9

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Finish IMs and IRMs
  • Build 1xRM
  • Glue SR3 mirror?

Plan for week of 4/16

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • Start SR3 Hang?

Plan for week of 4/23

  • Shoda-san at Mitaka
  • Fujii-san at Mitaka?
  • Tanioka-san at Mitaka?
  • Others at Kamioka
  • --
  • F0 blade prototype test

Plan for week of 4/30

  • Golden Week!

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Fabian vacation, 3/26-4/27 (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)