Line 6: Line 6:
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
==== Report for week of 1/15 ====
 * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
 * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
 * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
 * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
 * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
 * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
 * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
 * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
 * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
 
==== Plan for week of 1/22 ====
 * Fix or swap BF.
 * Route selected cables to flange.
 * Test IM picos and BF yaw pico.
Line 9: Line 22:
 * Enzo and Fabian routed all the SF/... cabling up past the SF and anchored it to the PI.
 * Enzo and Fabian moved the vacuum feedthroughs to new positions on the assembly frame corresponding more closely to the positions on the tank.
 * Hirata-san received the LBB blades back from additional machining, and he and Mark characterized them, and chose the 3 that were most closely matched. The total load capacity is 294 kg, which is rather larger than the 202 kg for the LBB and intermediate ring.
 * Mark measured all the coil resistances for the LVDTs and steppers on the PI to check everything was wired properly.
 * Hirata-san received the outrigger plates for the LBB black from additional machining to add helicoils but discovered that they were not M16 fine pitch but M16 regular. He sent them off again to be corrected.
 * Mark and Hirata-san inspected the vacuum tank and discovered that the top section is on backwards relative to the 3D CAD so that the jacks supporting the tank and the jacks supporting the PI via bellows are interchanged. We decided that, for the test hang, we would put the suspension in with a 135° anticlockwise rotation (instead of a 45° clockwise one). For the final hang, we will build the suspension with the BS/RM section backwards.
 * Fabian moved the F0 trim mass from on top of the F0 keystone and anchored it to the SF, keeping about 0.5 kg in reserve to allow for the weight of the SF-PI cables.
 * Enzo, Fabian and Hirata-san rearranged the in-air cabling for the OSEMs to match changes to the in-vacuum cables.
 * Hirata-san assembled the rods for the LBB and LBB damper.
 * Mark released new editions of E1503600 (BS circuit diagram) and E1503901 (in-vacuum cable detail) and updated Sato-san's cable spreadsheet.
==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Line 20: Line 30:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 6/6:
 * Cabling:
  * Finish moving in-air cabling to match feedthrough positions.
  * Cable and test PI vertical LVDT.
  * Calibrate PI vertical LVDT.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.

Week of 6/12:
 * Remove -Y flange cover, replace with cloth cover (or foil).
 * Prepare LBB.
  * Wipe LBB.
  * Loosen or remove LBB hold-down bolts.
  * Attach LBB outriggers and rod receptacles.
  * Lay out slings for LBB damper rings.
 * Prepare LBB damper support.
  * Install rods for LBB magnet ring.
  * Install safety rods for LBB Cu ring.
 * Prepare LBB Cu ring.
  * Pass into tank.
  * Reassemble on top of slings.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Assemble temporarily.
  * Attach magnets with template.
  * Disassemble.
  * Pass into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Pass sling ends through loops to bind LBB damper rings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Cabling, cabling, cabling.
==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/15

  • We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
  • Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
  • We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
  • We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
  • We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
  • We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
  • We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
  • Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
  • Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.

Plan for week of 1/22

  • Fix or swap BF.
  • Route selected cables to flange.
  • Test IM picos and BF yaw pico.

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.