==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
==== Report for week of 2/26 ====
 * We routed all the cables from the BF level up via the flying saucer to the SF.
 * Hirata-san tried filing the SF cap to improve the fit, but without much success.
 * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
 * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
 * We worked on recovering the IM OSEM alignment.
Line 15: Line 13:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Finish recovering IM OSEM alignment.
 * Calibrate SF LVDT.
 * Lift SF/... section and check total mass and balance.
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * Set up for rebuilding of two BFs.
Line 18: Line 25:
Week of 6/6:
 * Cabling:
  * Finish moving in-air cabling to match feedthrough positions.
  * Cable and test PI vertical LVDT.
  * Calibrate PI vertical LVDT.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri, then Mitaka.
 * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
 * Others Kamioka Mon-Thu
 * Install boxes in SR3 and SRM racks.
 * Lay SR3 in-air cabling.
 * Continue rebuild of BFs.
Line 30: Line 34:
Week of 6/12:
 * Remove -Y flange cover, replace with cloth cover (or foil).
 * Prepare LBB.
  * Wipe LBB.
  * Loosen or remove LBB hold-down bolts.
  * Attach LBB outriggers and rod receptacles.
  * Lay out slings for LBB damper rings.
 * Prepare LBB damper support.
  * Install rods for LBB magnet ring.
  * Install safety rods for LBB Cu ring.
 * Prepare LBB Cu ring.
  * Pass into tank.
  * Reassemble on top of slings.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Assemble temporarily.
  * Attach magnets with template.
  * Disassemble.
  * Pass into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Pass sling ends through loops to bind LBB damper rings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Cabling, cabling, cabling.
==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * All others at Mitaka
 * Make two sets of IM OSEMs
 * Make last in-air pico adapter cable
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Set up Dummy BS prism removal.

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Shoda-san at Mitaka
 * Others at Kamioka
 * --
 * F0 Prototype Blade Test
  * Characterize blades.
  * Choose best set of three.
  * Remove cracked blades from filter in SRM area.
  * Set up test weights in SRM area, first floor.
  * Remove floor panel in SRM area, second floor.
  * Install chosen blades.
  * Measure load capacity.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
 * Hirata-san vacation, Mon 3/5.
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 2/26

  • We routed all the cables from the BF level up via the flying saucer to the SF.
  • Hirata-san tried filing the SF cap to improve the fit, but without much success.
  • Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables.
  • We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.)
  • We worked on recovering the IM OSEM alignment.

Plan for week of 3/5

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Others at Kamioka.
  • -
  • Remove LBB temporary ballast masses from BS chamber.

  • Finish recovering IM OSEM alignment.
  • Calibrate SF LVDT.
  • Lift SF/... section and check total mass and balance.
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • Set up for rebuilding of two BFs.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri, then Mitaka.
  • Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri
  • Others Kamioka Mon-Thu
  • Install boxes in SR3 and SRM racks.
  • Lay SR3 in-air cabling.
  • Continue rebuild of BFs.

Plan for week of 3/19

  • Mark at LVC meeting
  • All others at Mitaka
  • Make two sets of IM OSEMs
  • Make last in-air pico adapter cable
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Set up Dummy BS prism removal.

Plan for week of 3/26

  • Mark vacation.
  • Shoda-san at Mitaka
  • Others at Kamioka
  • --
  • F0 Prototype Blade Test
    • Characterize blades.
    • Choose best set of three.
    • Remove cracked blades from filter in SRM area.
    • Set up test weights in SRM area, first floor.
    • Remove floor panel in SRM area, second floor.
    • Install chosen blades.
    • Measure load capacity.

To-Do Lists, Schedule

Vacation Info

  • Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
  • Hirata-san vacation, Mon 3/5.
  • Fabian vacation, 3/26-4/27 (then gone).