Differences between revisions 155 and 164 (spanning 9 versions)
Revision 155 as of 2017-06-09 13:41:18
Size: 2668
Editor: MarkBarton
Comment:
Revision 164 as of 2017-07-07 13:38:49
Size: 3274
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).
Line 15: Line 12:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.
Line 18: Line 24:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Document LVDT driver rebuild and other changes.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Design/install matrices, blend filters and damping filters.
 * Finish tidying rack and labeling cables.
 * Add temporary ballast to LBB and find total required.
 * Try rearranging arc weights to make room for magic wand.
 * Start on creating SR3 rack.
 * Preparation for BF rebuild.
 
Fabian, Hirata-san at Mitaka.
 * Clean BS secondary prisms and modified gluing jigs (Hirata-san).
 * Ship gluing tools and BS to Kamioka.
 * Do new 3D CAD for final BS install (Hirata-san):
  * On-assembly-frame version.
  * In-tank version.
 * Design SR assembly frame (Fabian).
 * Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
 * Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
 * Do mass budget for LBB - design ballast masses (Fabian)

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Enzo):

  • Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
  • Enzo worked on the final cabling plan for BS and SRx.
  • Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).

At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):

  • We glued magnets into their holders.
  • We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
  • We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
  • Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
  • We practiced putting sapphire prisms on the BS but didn't apply glue.
  • We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
  • We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
  • Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
  • We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
  • Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.

Plan for weeks of 7/10, 7/17

Mark, Enzo mostly at Kamioka.

  • More TFs.
  • Receive BS at Kamioka, do gluing if possible.
  • Document LVDT driver rebuild and other changes.
  • Learn how Miyo-kun's pico driver software works and make fixes/improvements.
  • Design/install matrices, blend filters and damping filters.
  • Finish tidying rack and labeling cables.
  • Add temporary ballast to LBB and find total required.
  • Try rearranging arc weights to make room for magic wand.
  • Start on creating SR3 rack.
  • Preparation for BF rebuild.

Fabian, Hirata-san at Mitaka.

  • Clean BS secondary prisms and modified gluing jigs (Hirata-san).
  • Ship gluing tools and BS to Kamioka.
  • Do new 3D CAD for final BS install (Hirata-san):
    • On-assembly-frame version.
    • In-tank version.
  • Design SR assembly frame (Fabian).
  • Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
  • Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
  • Do mass budget for LBB - design ballast masses (Fabian)

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)