Differences between revisions 155 and 188 (spanning 33 versions)
Revision 155 as of 2017-06-09 13:41:18
Size: 2668
Editor: MarkBarton
Comment:
Revision 188 as of 2017-09-08 14:22:47
Size: 2571
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We characterized the remachined LBB blades, chose three and installed them in the LBB blade units in the PI.
 * We removed all sticky labels from the PI and cleaned the affected areas (and as much as possible of the rest of the surface) with ethanol.
 * We rearranged the arc weights on the PI to make space for the magic wand and installed the magic wand.
 * We rearranged the magnets on the SF damper ring to suit three Cu segments (instead of two as in the test hang).
 * We put proper vacuum-compatible tubing around all the stepper motor connections on the top of the PI (replacing cling wrap).
 * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
 * We closed the BF, craned the SF back in, and hooked the BF/..., this time with the hex cable clamp.
 * We routed cables from the BF via the hex cable clamp to the SF level.
 * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
 * We adjusted all the IRM OSEMs laterally and in/out.
 * We calibrated the SF LVDT and tested the SF FR stepper.
 * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we had to lift it with slings and could not accurately trim it for pitch/roll.
 * Therefore we brought forward the craning in of the PI with the SF damper ring hanging from it.
 * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right considering the hex cable clamp and cables.
 * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
Line 15: Line 24:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 9/4 ====
==== Plan for week of 9/13 ====
Mark (except Wed), Fabian (except Mon, Tue), Enzo, Ohishi-san (except Mon-Wed), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Reinstall F0-SF rod, this time with hex cable clamp.
 * Route cables.
 * Adjust SF trim mass, adjust tilt and vertical.
 * Adjust SF damper gap.
 * Cable and test IP LVDTs.
 * Cable and test F0 LVDT.
 * Cable and test PI steppers.
 * Cable and test geophones.
 *
  
Line 18: Line 38:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We characterized the remachined LBB blades, chose three and installed them in the LBB blade units in the PI.
  • We removed all sticky labels from the PI and cleaned the affected areas (and as much as possible of the rest of the surface) with ethanol.
  • We rearranged the arc weights on the PI to make space for the magic wand and installed the magic wand.
  • We rearranged the magnets on the SF damper ring to suit three Cu segments (instead of two as in the test hang).
  • We put proper vacuum-compatible tubing around all the stepper motor connections on the top of the PI (replacing cling wrap).
  • We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
  • We closed the BF, craned the SF back in, and hooked the BF/..., this time with the hex cable clamp.
  • We routed cables from the BF via the hex cable clamp to the SF level.
  • We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
  • We adjusted all the IRM OSEMs laterally and in/out.
  • We calibrated the SF LVDT and tested the SF FR stepper.
  • We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we had to lift it with slings and could not accurately trim it for pitch/roll.
  • Therefore we brought forward the craning in of the PI with the SF damper ring hanging from it.
  • We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right considering the hex cable clamp and cables.
  • However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.

Plan for week of 9/4

Plan for week of 9/13

Mark (except Wed), Fabian (except Mon, Tue), Enzo, Ohishi-san (except Mon-Wed), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Reinstall F0-SF rod, this time with hex cable clamp.
  • Route cables.
  • Adjust SF trim mass, adjust tilt and vertical.
  • Adjust SF damper gap.
  • Cable and test IP LVDTs.
  • Cable and test F0 LVDT.
  • Cable and test PI steppers.
  • Cable and test geophones.