Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
 * We recounted the used and spare cables now that the in-vacuum cabling appears to be final.
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
 * Enzo traced the issue with the geophones to a specific cable.
 * We measured the BF and F0 GAS resonant frequencies.
 * We adjusted the spacing of the SR damper.
 * We double-checked the BS pitch with the OL.
 * We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
 * '''We prepared the suspension for lifting and craned it into the tank.'''
 * Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
 * Enzo and team moved all the in-air cables from the assembly frame to the tank.
 * Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.
 
==== Plan for week of 9/25 ====
Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Unlock rest of suspension and readjust.
 * Debug electronics.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Adjust LBB damper Cu-magnet gap.
 * Measure required ballast for LBB.
 * Remove First Contact, try OL.
 * Prepare for SR2 work.
Line 16: Line 31:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo, Fabian, Ohishi-san.
 * TFs etc.
Mitaka: Hirata-san?
 * SF design/purchasing.
Line 19: Line 37:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Vacation Info ====
Mark: 10/16-24
Enzo: 9/27-29

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
  • Enzo traced the issue with the geophones to a specific cable.
  • We measured the BF and F0 GAS resonant frequencies.
  • We adjusted the spacing of the SR damper.
  • We double-checked the BS pitch with the OL.
  • We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
  • We prepared the suspension for lifting and craned it into the tank.

  • Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
  • Enzo and team moved all the in-air cables from the assembly frame to the tank.
  • Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.

Plan for week of 9/25

Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Unlock rest of suspension and readjust.
  • Debug electronics.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Adjust LBB damper Cu-magnet gap.
  • Measure required ballast for LBB.
  • Remove First Contact, try OL.
  • Prepare for SR2 work.

Plan for week of 10/2

Kamioka: Mark, Enzo, Fabian, Ohishi-san.

  • TFs etc.

Mitaka: Hirata-san?

  • SF design/purchasing.