Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.
 * We recounted the used and spare cables now that the in-vacuum cabling appears to be final.
Line 16: Line 8:
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
 * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
 * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
 * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
 * Enzo found nearly all in-vacuum cables.
 * Enzo and Shoda-san got several more loops closed on the BS.
 * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
 * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
 * Hirata-san worked on SR procurement.
 * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
 
==== Plan for week of 12/4 ====
 * Mark at Kamioka.
 * Fabian at f2f satellite meeting Mon, then Kamioka.
 * Enzo at f2f then Mitaka.
 * Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
 * Kozu-kun Thu only.
 * Mirror gluing.
 * IM assembly and pico test.
Line 19: Line 27:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
 * Kozu-kun Mon-Thu only.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo TBD, probably 12/22-1/3
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
  • Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
  • Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
  • Enzo found nearly all in-vacuum cables.
  • Enzo and Shoda-san got several more loops closed on the BS.
  • Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
  • Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
  • Hirata-san worked on SR procurement.
  • Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.

Plan for week of 12/4

  • Mark at Kamioka.
  • Fabian at f2f satellite meeting Mon, then Kamioka.
  • Enzo at f2f then Mitaka.
  • Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
  • Kozu-kun Thu only.
  • Mirror gluing.
  • IM assembly and pico test.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
  • Kozu-kun Mon-Thu only.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo TBD, probably 12/22-1/3
  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)