Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Hirata-san): * Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag. * Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI. * Hirata-san recounted all the unused cables. * Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring. * Enzo and Mark tested all the stepper motors. * Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card. * Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws. * Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one). * ==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece. * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework. * We pulled out all the old in-air cabling. * We laid about 9 new in-air cables. * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon. * We connected up, tested and calibrated the BF LVDT. * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday. At Mitaka (Hirata-san: * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost. * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far). * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation. * He liaised with Koshin-shoko about modification of BS LBB blade springs. * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing. * He worked on the 3D model of SR3 SUS wires, and making a list for quotation. |
Line 20: | Line 23: |
Week of 6/12: * Cabling: * Debug/fix PI vertical LVDTs #0 and #2. * Calibrate PI vertical LVDT. * Debug/fix geophone #1. * Set yoke on PI vertical LVDT (if necessary). * Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. * Calibrate PI horizontal LVDTs. * Prepare LBB. * Attach LBB outriggers and rod receptacles. * Prepare LBB Cu ring. * Remove from tank, fix incompletely threaded holes, reinstall in tank. * Lay down spacers to protect magnets (in next step). * Prepare LBB magnet ring. * Disassemble. * Pass pieces into tank. * Reassemble on top of Cu ring. * Install LBB damper. * Bind LBB damper rings together with slings. * Remove vacuum tank lid and ring. * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method. * Crane suspension into tank. * Hook LBB Cu ring. * Hook LBB. * Crane vacuum tank lid+ring black on. * Remove vacuum tank lid (only). * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring. * Reconnect in-air cables. |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; readjust height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * (Time permitting) Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. ==== Plan for week of 8/28 ==== Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * Suspend BF/IRM/IM/RM/BS. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
- We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
- We pulled out all the old in-air cabling.
- We laid about 9 new in-air cables.
- We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
- We connected up, tested and calibrated the BF LVDT.
- We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
At Mitaka (Hirata-san:
- Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
- He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
- He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
- He liaised with Koshin-shoko about modification of BS LBB blade springs.
- He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
- He worked on the 3D model of SR3 SUS wires, and making a list for quotation.
Plan for week of 8/21
Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
- Swap in new IM ballast masses; readjust height and levelness.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- (Time permitting) Try TFs with optical sensors.
Mitaka: Hirata-san.
- SR stuff.
Plan for week of 8/28
Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
- Suspend BF/IRM/IM/RM/BS.
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct