At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag.
 * Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI.
 * Hirata-san recounted all the unused cables.
 * Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring.
 * Enzo and Mark tested all the stepper motors.
 * Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card.
 * Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws.
 * Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one).
 *
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):
 * We moved all the in-air cables over to the tank.
 * We plugged all the in-air and in-vacuum cables into the feedthroughs and checked that we got signals from all the output channels (actuation not yet tested). We had to work around a snag with the new F-F gender changers that replace many Type 1 and Type 2 cables: like the vacuum feedthroughs, they flip pins 1 and 5. Electrically they could just be omitted, but the in-air cables don't plug directly into the feedthroughs very well, so we made up some non-flipping adapters similar to the anti-feedthrough adapters.
 * Hirata-san fixed a problem with one of the rods supporting the LBB Cu ring, where the head was not seating in the receptacle at the bottom. The head was slightly bent so he just reinstalled the rod upside-down to move the bent head to a less critical spot. (This also establishes that it's possible to install the rods later if we need to, although it's more convenient to bring them in with the suspension on the crane as we've been doing it.)
 * We suspended the LBB. Per a request from Akutsu-san, we set it as high as we easily could. We decided to try for 30 mm higher than in the CAD, for a height of 367 (instead of 397) mm for the beam line above the LBB. 40 mm would also be doable, but any more would need new rods, and more than ≈100 mm would cause the LBB to hit the bottom of the security structure.
 * We moved a lot of stuff out of the +X side of the cleanbooth to behind SRM, so that Mirapro could connect the section of beam duct between the BS tank and the X arm. They put the new section in position but have not connected it up yet.
 * Hirata-san worked with Mirapro to get the SR assembly frame assembled in the SR3 area. (Insertion of the LBB and installation of the top of the tank is planned for 10/18-20.)
 * We investigated a problem with the IM OSEM readings, which were far from mid-range. Although Fabian and Ohishi-san got the payload hanging nicely on Thu 9/21, sometime between then and when we plugged the OSEMs back in on 9/28, the BF and IRM apparently tipped considerably (with the +X corner high) so that the H2 and H3 OSEM flags are fouling on the bottom and top of their respective OSEMs.
 * We took the service ports off the BF tank at the BF level and trying correcting the tilt by moving the sliding masses around, but to no avail. Finally Hirata-san solved it by noticing that one of the BF-IRM rods was not seated properly at the top. Because it had been correct, and couldn't have fallen upwards, it must have gotten knocked during the LBB adjustment work. We locked the BF temporarily, lifted the corner of the IRM and jiggled the rod. It fell back into place and the alignment was much better. We backed out the sliding mass adjustments and it was back to normal.
Line 20: Line 17:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.
 * Finish preparation for SR2 work.
 * Debug electronics, especially actuation.
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
Mitaka: Fabian, Hirata-san
 * Design ballast for LBB.
 * Design improved PI yaw adjustment.
 * SR procurement.

==== Plan for week of 10/10 ====
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * TFs, final preparation for alignment in week of 10/16.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Work with alignment team.

==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):

  • We moved all the in-air cables over to the tank.
  • We plugged all the in-air and in-vacuum cables into the feedthroughs and checked that we got signals from all the output channels (actuation not yet tested). We had to work around a snag with the new F-F gender changers that replace many Type 1 and Type 2 cables: like the vacuum feedthroughs, they flip pins 1 and 5. Electrically they could just be omitted, but the in-air cables don't plug directly into the feedthroughs very well, so we made up some non-flipping adapters similar to the anti-feedthrough adapters.
  • Hirata-san fixed a problem with one of the rods supporting the LBB Cu ring, where the head was not seating in the receptacle at the bottom. The head was slightly bent so he just reinstalled the rod upside-down to move the bent head to a less critical spot. (This also establishes that it's possible to install the rods later if we need to, although it's more convenient to bring them in with the suspension on the crane as we've been doing it.)
  • We suspended the LBB. Per a request from Akutsu-san, we set it as high as we easily could. We decided to try for 30 mm higher than in the CAD, for a height of 367 (instead of 397) mm for the beam line above the LBB. 40 mm would also be doable, but any more would need new rods, and more than ≈100 mm would cause the LBB to hit the bottom of the security structure.
  • We moved a lot of stuff out of the +X side of the cleanbooth to behind SRM, so that Mirapro could connect the section of beam duct between the BS tank and the X arm. They put the new section in position but have not connected it up yet.
  • Hirata-san worked with Mirapro to get the SR assembly frame assembled in the SR3 area. (Insertion of the LBB and installation of the top of the tank is planned for 10/18-20.)
  • We investigated a problem with the IM OSEM readings, which were far from mid-range. Although Fabian and Ohishi-san got the payload hanging nicely on Thu 9/21, sometime between then and when we plugged the OSEMs back in on 9/28, the BF and IRM apparently tipped considerably (with the +X corner high) so that the H2 and H3 OSEM flags are fouling on the bottom and top of their respective OSEMs.
  • We took the service ports off the BF tank at the BF level and trying correcting the tilt by moving the sliding masses around, but to no avail. Finally Hirata-san solved it by noticing that one of the BF-IRM rods was not seated properly at the top. Because it had been correct, and couldn't have fallen upwards, it must have gotten knocked during the LBB adjustment work. We locked the BF temporarily, lifted the corner of the IRM and jiggled the rod. It fell back into place and the alignment was much better. We backed out the sliding mass adjustments and it was back to normal.

Plan for week of 10/2

Kamioka: Mark, Enzo (Tue-Fri), Ohishi-san, Kozu-kun.

  • Finish preparation for SR2 work.
  • Debug electronics, especially actuation.
  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.

Mitaka: Fabian, Hirata-san

  • Design ballast for LBB.
  • Design improved PI yaw adjustment.
  • SR procurement.

Plan for week of 10/10

Holiday Mon 10/9, Open Day prep Fri 10/13.

  • TFs, final preparation for alignment in week of 10/16.

Plan for week of 10/16

Kamioka: all but Mark

  • Work with alignment team.