2949
Comment:
|
1551
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Hirata-san): * Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag. * Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI. * Hirata-san recounted all the unused cables. * Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring. * Enzo and Mark tested all the stepper motors. * Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card. * Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws. * Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one). * Enzo and Mark tested the pico motors. The software is very unreliable, but we we able to confirm that the IM pitch pico works. * The whole team wrapped items and shut down equipment ahead of the power outage. ==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. |
Line 21: | Line 16: |
Week of 6/12: * Cabling: * Debug/fix PI vertical LVDTs #0 and #2. * Calibrate PI vertical LVDT. * Debug/fix geophone #1. * Set yoke on PI vertical LVDT (if necessary). * Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. * Calibrate PI horizontal LVDTs. * Prepare LBB. * Attach LBB outriggers and rod receptacles. * Prepare LBB Cu ring. * Remove from tank, fix incompletely threaded holes, reinstall in tank. * Lay down spacers to protect magnets (in next step). * Prepare LBB magnet ring. * Disassemble. * Pass pieces into tank. * Reassemble on top of Cu ring. * Install LBB damper. * Bind LBB damper rings together with slings. * Remove vacuum tank lid and ring. * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method. * Crane suspension into tank. * Hook LBB Cu ring. * Hook LBB. * Crane vacuum tank lid+ring black on. * Remove vacuum tank lid (only). * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring. * Reconnect in-air cables. |
==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish disassembly. * Finish BF rebuild. * Remove LBB rings. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. ==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
- We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
- Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
- We craned the PI. There was a minor safety incident - see below.
- Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
- Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
- We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
- We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Plan for week of 7/24
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
- Check results of gluing.
- Finish disassembly.
- Finish BF rebuild.
- Remove LBB rings.
- Recheck alignment of assembly frame and centering of optical table.
- Install IM, suspend BS and RM.
Plan for week of 7/31
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
- Weigh/trim BS/RM/IM.
- Bring in rebuilt BF.
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct