Differences between revisions 158 and 174 (spanning 16 versions)
Revision 158 as of 2017-06-16 13:36:45
Size: 2949
Editor: MarkBarton
Comment:
Revision 174 as of 2017-08-04 13:28:54
Size: 1876
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag.
 * Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI.
 * Hirata-san recounted all the unused cables.
 * Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring.
 * Enzo and Mark tested all the stepper motors.
 * Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card.
 * Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws.
 * Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one).
 * Enzo and Mark tested the pico motors. The software is very unreliable, but we we able to confirm that the IM pitch pico works.
 * The whole team wrapped items and shut down equipment ahead of the power outage.
==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
 * We reconfigured the top of the assembly frame.
 * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
 * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
 * We re-installed, centered and leveled the IM.
 * We solved two issues with the new wire clamps:
  * Some holes were not properly threaded - Hirata-san retapped them.
  * Some locating pins were loose - we glued them.
 * We mounted the BS mirror box on the trolley and brought it under the IM.
 * We installed the winch system and the 300 µm wires for the BS.
 * We set up the optical lever.
 * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
 * We suspended the BS and set its height and pitch.
Line 21: Line 21:
Week of 6/12:
 * Cabling:
  * Debug/fix PI vertical LVDTs #0 and #2.
  * Calibrate PI vertical LVDT.
  * Debug/fix geophone #1.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.
 * Prepare LBB.
  * Attach LBB outriggers and rod receptacles.
 * Prepare LBB Cu ring.
  * Remove from tank, fix incompletely threaded holes, reinstall in tank.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Disassemble.
  * Pass pieces into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Bind LBB damper rings together with slings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-air cables.
==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>>
 * Adjust RM OSEMs; add new RM cable clamp piece.
 * Hang RM.
 * Run new (longer) OSEM cables.
 * Weigh/trim BS/RM/IM.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR stuff.

==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>>
 * Bring in BF and hang BS/RM/IM/IRM.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff?
Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):

  • We reconfigured the top of the assembly frame.
  • We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
  • We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
  • We re-installed, centered and leveled the IM.
  • We solved two issues with the new wire clamps:
    • Some holes were not properly threaded - Hirata-san retapped them.
    • Some locating pins were loose - we glued them.
  • We mounted the BS mirror box on the trolley and brought it under the IM.
  • We installed the winch system and the 300 µm wires for the BS.
  • We set up the optical lever.
  • Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
  • We suspended the BS and set its height and pitch.

Plan for week of 8/7

Site closure: Friday
Vacation: Enzo (Mon), Fabian (Mon-Fri)
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).

  • Adjust RM OSEMs; add new RM cable clamp piece.
  • Hang RM.
  • Run new (longer) OSEM cables.
  • Weigh/trim BS/RM/IM.
  • Suspend BS/RM/IM, add IRM.
  • Lay new in-air OSEM cables.

Mitaka: Hirata-san (Mon-Fri)

  • SR stuff.

Plan for week of 8/14

Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).

  • Bring in BF and hang BS/RM/IM/IRM.

Mitaka: Hirata-san (Mon-Fri)

  • SR Stuff?

Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)