Size: 2949
Comment:
|
Size: 1817
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Hirata-san): * Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag. * Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI. * Hirata-san recounted all the unused cables. * Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring. * Enzo and Mark tested all the stepper motors. * Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card. * Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws. * Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one). * Enzo and Mark tested the pico motors. The software is very unreliable, but we we able to confirm that the IM pitch pico works. * The whole team wrapped items and shut down equipment ahead of the power outage. ==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. |
==== Report for week of 1/15 ==== * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL. * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs. * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget. * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF. * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF. * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side). * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g. * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs. * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in. ==== Plan for week of 1/22 ==== * Fix or swap BF. * Route selected cables to flange. * Test IM picos and BF yaw pico. |
Line 21: | Line 22: |
Week of 6/12: * Cabling: * Debug/fix PI vertical LVDTs #0 and #2. * Calibrate PI vertical LVDT. * Debug/fix geophone #1. * Set yoke on PI vertical LVDT (if necessary). * Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. * Calibrate PI horizontal LVDTs. * Prepare LBB. * Attach LBB outriggers and rod receptacles. * Prepare LBB Cu ring. * Remove from tank, fix incompletely threaded holes, reinstall in tank. * Lay down spacers to protect magnets (in next step). * Prepare LBB magnet ring. * Disassemble. * Pass pieces into tank. * Reassemble on top of Cu ring. * Install LBB damper. * Bind LBB damper rings together with slings. * Remove vacuum tank lid and ring. * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method. * Crane suspension into tank. * Hook LBB Cu ring. * Hook LBB. * Crane vacuum tank lid+ring black on. * Remove vacuum tank lid (only). * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring. * Reconnect in-air cables. |
==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/15
- We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
- Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
- We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
- We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
- We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
- We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
- We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
- Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
- Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
Plan for week of 1/22
- Fix or swap BF.
- Route selected cables to flange.
- Test IM picos and BF yaw pico.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2