Line 7: Line 7:
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * We disconnected the in-vacuum and in-air cabling from the feedthroughs.
 * We removed crossbars below BF and SF.
 * We set the SF damper to 4 mm clearance.
 * We adjusted the jacks to nominal height.
 * We removed the geophones and PI yaw stepper for craning.
 * We craned the suspension into the tank, and hooked the LBB Cu ring.
 * We replaced the geophones etc.
 * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
 * We unlocked the IP and adjusted to to center with the jacks and fishing rods.
 * We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
 * We unclamped the LBB damper rings and removed the spacers.
 * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
 * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
 * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
 * We reconnected all but four of the in-air cables.
At Kamioka (Mark, Enzo, Yoshioka-kun):
 * We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
 * We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
 * We put the blocks back under the LBB and unhooked it.
 * We moved the suspension from the tank back to the assembly frame.
 * We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
 * We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
 * We checked the centering of the security frame in the assembly frame and disconnected it from the PI. One M12x35 screw galled after a few turns and will need attention.
 * Enzo started setting up the SR3 rack (with help from Yamamoto-san).
 * We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.
Line 24: Line 18:
==== Plan for week of 6/26 ====
Mark and Enzo at Kamioka:
 * Double-check where gender-benders were used.
 * Finish connecting in-air cabling.
 * Debug all cabling.
 * Work with Simon to set up LSOL.
Fabian at Mitaka:
 * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
 * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).
Hirata-san at Mitaka:
 * Do new 3D CAD:
  * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
  * Final BS build, as above, but with everything BF down rotated back to original.
   * In-tank version.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)
At Mitaka (Fabian and Hirata-san):
 * Hirata-san shipped the optic and gluing tools to Kamioka.
 * Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
 * Fabian worked on the SRx assembly frame.

==== Plan for week of 7/18 ====
Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).
 * Glue prisms/magnets on BS.
 * Dismantle suspension.
 * Finish setting up filter service area (mostly already done by Mirapro).
 * Move BF to filter service area, start rebuild.

==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Finish BF rebuild.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.

Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Enzo, Yoshioka-kun):

  • We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
  • We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
  • We put the blocks back under the LBB and unhooked it.
  • We moved the suspension from the tank back to the assembly frame.
  • We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
  • We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
  • We checked the centering of the security frame in the assembly frame and disconnected it from the PI. One M12x35 screw galled after a few turns and will need attention.
  • Enzo started setting up the SR3 rack (with help from Yamamoto-san).
  • We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.

At Mitaka (Fabian and Hirata-san):

  • Hirata-san shipped the optic and gluing tools to Kamioka.
  • Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
  • Fabian worked on the SRx assembly frame.

Plan for week of 7/18

Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).

  • Glue prisms/magnets on BS.
  • Dismantle suspension.
  • Finish setting up filter service area (mostly already done by Mirapro).
  • Move BF to filter service area, start rebuild.

Plan for week of 7/24

Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).

  • Finish BF rebuild.
  • Recheck alignment of assembly frame and centering of optical table.
  • Install IM, suspend BS and RM.

Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct