At Kamioka (Mark, Fabian, Enzo, Hirata-san): * We disconnected the in-vacuum and in-air cabling from the feedthroughs. * We removed crossbars below BF and SF. * We set the SF damper to 4 mm clearance. * We adjusted the jacks to nominal height. * We removed the geophones and PI yaw stepper for craning. * We craned the suspension into the tank, and hooked the LBB Cu ring. * We replaced the geophones etc. * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure. * We unlocked the IP and adjusted to to center with the jacks and fishing rods. * We craned the vacuum tank lid+ring back on, and then removed just the lid (only). * We unclamped the LBB damper rings and removed the spacers. * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring. * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips. * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender. * We reconnected all but four of the in-air cables. |
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. |
Line 24: | Line 16: |
==== Plan for week of 6/26 ==== Mark and Enzo at Kamioka: * Double-check where gender-benders were used. * Finish connecting in-air cabling. * Debug all cabling. * Work with Simon to set up LSOL. Fabian at Mitaka: * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable). * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc). Hirata-san at Mitaka: * Do new 3D CAD: * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed. * Final BS build, as above, but with everything BF down rotated back to original. * In-tank version. * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.) * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.) |
==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish BF rebuild. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. ==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
- We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it.
- Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it.
- We craned the PI. There was a minor safety incident - see below.
- Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3).
- Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one.
- We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing.
- We set up the BS gluing jigs and applied the glue. We will check the results on Monday.
Plan for week of 7/24
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
- Check results of gluing.
- Finish BF rebuild.
- Recheck alignment of assembly frame and centering of optical table.
- Install IM, suspend BS and RM.
Plan for week of 7/31
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
- Weigh/trim BS/RM/IM.
- Bring in rebuilt BF.
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct