Size: 2225
Comment:
|
Size: 1135
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Hirata-san): * We disconnected the in-vacuum and in-air cabling from the feedthroughs. * We removed crossbars below BF and SF. * We set the SF damper to 4 mm clearance. * We adjusted the jacks to nominal height. * We removed the geophones and PI yaw stepper for craning. * We craned the suspension into the tank, and hooked the LBB Cu ring. * We replaced the geophones etc. * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure. * We unlocked the IP and adjusted to to center with the jacks and fishing rods. * We craned the vacuum tank lid+ring back on, and then removed just the lid (only). * We unclamped the LBB damper rings and removed the spacers. * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring. * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips. * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender. * We reconnected all but four of the in-air cables. |
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs. * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IM |
Line 24: | Line 13: |
==== Plan for week of 6/26 ==== Mark and Enzo at Kamioka: * Double-check where gender-benders were used. * Finish connecting in-air cabling. * Debug all cabling. * Work with Simon to set up LSOL. Fabian at Mitaka: * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable). * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc). Hirata-san at Mitaka: * Do new 3D CAD: * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed. * Final BS build, as above, but with everything BF down rotated back to original. * In-tank version. * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.) * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.) |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
- We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
- We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
- We aligned the IM
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct