Size: 2225
Comment:
|
Size: 1533
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Enzo, Hirata-san): * We disconnected the in-vacuum and in-air cabling from the feedthroughs. * We removed crossbars below BF and SF. * We set the SF damper to 4 mm clearance. * We adjusted the jacks to nominal height. * We removed the geophones and PI yaw stepper for craning. * We craned the suspension into the tank, and hooked the LBB Cu ring. * We replaced the geophones etc. * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure. * We unlocked the IP and adjusted to to center with the jacks and fishing rods. * We craned the vacuum tank lid+ring back on, and then removed just the lid (only). * We unclamped the LBB damper rings and removed the spacers. * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring. * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips. * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender. * We reconnected all but four of the in-air cables. |
|
Line 24: | Line 8: |
==== Plan for week of 6/26 ==== Mark and Enzo at Kamioka: * Double-check where gender-benders were used. * Finish connecting in-air cabling. * Debug all cabling. * Work with Simon to set up LSOL. Fabian at Mitaka: * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable). * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc). Hirata-san at Mitaka: * Do new 3D CAD: * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed. * Final BS build, as above, but with everything BF down rotated back to original. * In-tank version. * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.) * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.) |
* Mark worked on SR2 planning. * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436). * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out. * Hirata-san ordered more disks for IM flags. * Hirata-san asked for quotes on SF LBB blades. * Hirata-san got a reduced quote for the LBB damper rings. * Hirata-san received and cleaned suspension wires for the SR. * Fabian worked on the SR mass budget. * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions. * Enzo and Kozu-kun worked on control filter design and installation. ==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation. * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly. * Mark from Mon lunchtime. * Kozu-kun from Mon lunchtime through Wed. * Mirror gluing. * SR2 rack setup. ==== Plan for week of 12/4 ==== * All at Kamioka * IM assembly and pico test. * Assembly frame alignment and optical table centering. * OL setup. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark worked on SR2 planning.
- Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
- Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
- Hirata-san ordered more disks for IM flags.
- Hirata-san asked for quotes on SF LBB blades.
- Hirata-san got a reduced quote for the LBB damper rings.
- Hirata-san received and cleaned suspension wires for the SR.
- Fabian worked on the SR mass budget.
- Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
- Enzo and Kozu-kun worked on control filter design and installation.
Plan for week of 11/27
- Fabian at commissioning workshop
- Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
- All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
- Mark from Mon lunchtime.
- Kozu-kun from Mon lunchtime through Wed.
- Mirror gluing.
- SR2 rack setup.
Plan for week of 12/4
- All at Kamioka
- IM assembly and pico test.
- Assembly frame alignment and optical table centering.
- OL setup.
Vacation Info
- Mark 12/22-1/3
- Enzo TBD, probably 12/22-1/3
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)