Size: 2225
Comment:
|
Size: 1817
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Hirata-san): * We disconnected the in-vacuum and in-air cabling from the feedthroughs. * We removed crossbars below BF and SF. * We set the SF damper to 4 mm clearance. * We adjusted the jacks to nominal height. * We removed the geophones and PI yaw stepper for craning. * We craned the suspension into the tank, and hooked the LBB Cu ring. * We replaced the geophones etc. * We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure. * We unlocked the IP and adjusted to to center with the jacks and fishing rods. * We craned the vacuum tank lid+ring back on, and then removed just the lid (only). * We unclamped the LBB damper rings and removed the spacers. * We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring. * We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips. * We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender. * We reconnected all but four of the in-air cables. |
==== Report for week of 1/15 ==== * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL. * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs. * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget. * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF. * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF. * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side). * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g. * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs. * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in. ==== Plan for week of 1/22 ==== * Fix or swap BF. * Route selected cables to flange. * Test IM picos and BF yaw pico. |
Line 24: | Line 22: |
==== Plan for week of 6/26 ==== Mark and Enzo at Kamioka: * Double-check where gender-benders were used. * Finish connecting in-air cabling. * Debug all cabling. * Work with Simon to set up LSOL. Fabian at Mitaka: * Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable). * Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc). Hirata-san at Mitaka: * Do new 3D CAD: * BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed. * Final BS build, as above, but with everything BF down rotated back to original. * In-tank version. * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.) * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.) |
==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/15
- We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
- Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
- We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
- We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
- We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
- We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
- We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
- Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
- Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
Plan for week of 1/22
- Fix or swap BF.
- Route selected cables to flange.
- Test IM picos and BF yaw pico.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2