Line 5: Line 5:
 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]])
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]])

 * Type B Past Week Summary
  * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka.
  * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets.
  * Hirata-san worked on organizing:
   * Work platforms
   * Load gauge adapter and associated parts
   * Possible fall-back plans for the rods connecting the security structure to the PI.
 * Hirata-san:
  * Did drawings of SR damper.
 * Mark, Fabian, Enzo and Hirata-san (at Kamioka):
  * Took the end plate off the IM to get access to the pitch/roll picos.
  * Found the pitch pico was unreliable and replaced it.
  * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
  * Reassembled and rebalanced the IM.
  * Reassembled and adjusted the IRM.
  * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
  * Adjusted IM OSEMs to half-way.
  * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
  * Installed an improved LVDT cable made by Hirata-san.
  * Made and hung posters for the Elites meeting visitors.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Hirata-san:
    • Did drawings of SR damper.
  • Mark, Fabian, Enzo and Hirata-san (at Kamioka):
    • Took the end plate off the IM to get access to the pitch/roll picos.
    • Found the pitch pico was unreliable and replaced it.
    • Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
    • Reassembled and rebalanced the IM.
    • Reassembled and adjusted the IRM.
    • Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
    • Adjusted IM OSEMs to half-way.
    • Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
    • Installed an improved LVDT cable made by Hirata-san.
    • Made and hung posters for the Elites meeting visitors.