* Type B Past Week Summary * Flags and metal prisms ordered; expected 5/31. * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws): * Crane adapter * Lower breadboard blade module (with cable clamps) * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete) * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram) * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]]) * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]]) * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro. * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later). * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun): * We reconfigured the top of the assembly frame. * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces. * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys. * We re-installed, centered and leveled the IM. * We solved two issues with the new wire clamps: * Some holes were not properly threaded - Hirata-san retapped them. * Some locating pins were loose - we glued them. * We mounted the BS mirror box on the trolley and brought it under the IM. * We installed the winch system and the 300 µm wires for the BS. * We set up the optical lever. * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in. |
Line 18: | Line 20: |
* Type B Past Week Summary * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka. * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets. * Hirata-san worked on organizing: * Work platforms * Load gauge adapter and associated parts * Possible fall-back plans for the rods connecting the security structure to the PI. |
==== Plan for week of 8/7 ==== Site closure: Friday<<BR>> Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>> Mitaka: Hirata-san (Mon-Fri)<<BR>> Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>> * Finish hanging BS * Hang RM. * Weigh/trim BS/RM/IM. * Suspend BS/RM/IM, add IRM. * Lay new in-air OSEM cables. ==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>> Mitaka: Hirata-san (Mon-Fri)<<BR>> Vacation: Fabian (Mon-Fri) Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
- We reconfigured the top of the assembly frame.
- We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
- We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
- We re-installed, centered and leveled the IM.
- We solved two issues with the new wire clamps:
- Some holes were not properly threaded - Hirata-san retapped them.
- Some locating pins were loose - we glued them.
- We mounted the BS mirror box on the trolley and brought it under the IM.
- We installed the winch system and the 300 µm wires for the BS.
- We set up the optical lever.
- Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
Plan for week of 8/7
Site closure: Friday
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).
Mitaka: Hirata-san (Mon-Fri)
Vacation: Enzo (Mon), Fabian (Mon-Fri)
- Finish hanging BS
- Hang RM.
- Weigh/trim BS/RM/IM.
- Suspend BS/RM/IM, add IRM.
- Lay new in-air OSEM cables.
Plan for week of 8/14
Site closure: Mon, Tue
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).
Mitaka: Hirata-san (Mon-Fri)
Vacation: Fabian (Mon-Fri)
Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct