* Type B Past Week Summary * Flags and metal prisms ordered; expected 5/31. * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws): * Crane adapter * Lower breadboard blade module (with cable clamps) * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete) * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram) * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]]) * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]]) * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro. * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later). * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. |
Line 18: | Line 13: |
* Type B Past Week Summary * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka. * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets. * Hirata-san worked on organizing: * Work platforms * Load gauge adapter and associated parts * Possible fall-back plans for the rods connecting the security structure to the PI. |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * Shoda-san at Mitaka * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. ==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. ==== Plan for week of 2/26 ==== * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. ==== Vacation Info ==== * Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
- Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
- Fabian installed ballast masses in the BF.
- Mark worked on schedule.
- Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Plan for week of 2/13
- No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
- Shoda-san at Mitaka
- All others at Kamioka.
- -
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Enzo back from Tuesday.
- Shoda-san at Mitaka
- All others at Kamioka.
- -
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Plan for week of 2/26
- Add Cu segments to SF cap.
- Lift SF/... section and check total mass and balance.
Vacation Info
- Enzo 1/30-2/19.
- Fabian 4/2-4/27 vacation (then gone).