 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]])
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Report for week of 5/28 ====
 * Enzo and Mark debugged the BS BIO connections and finally got it working. There were a total of four issues identified:
  * A wrong block used in the BS real-time model.
  * The real-time model deciding to treat the cards as numbered backwards from the slot order or the jumper settings.
  * Two unlabeled cables that may have been swapped.
  * The GAS coil driver and associated cables had been labeled HPCD #1 whereas it had been #0 in the diagram.
 * Hirata-san and Kozu-kun received the final F0 blades, characterized 6 of them and, with help from Takahashi-san, installed a matched set of 3 into PI #3. It appears to be 6 kg short of the load capacity that was targeted, but still with 4 kg of margin. It is close to having a good frequency but needs another round of tuning.
 * Mark and Terrence fixed an issue with the security structure - due to a screenshot of the CAD not updated from the BS procedure to the SR one, the BF ring had been placed 180° off in yaw. We suspended the BF from the load gauge adapter, reconfigured the BF jacks to support the ring instead of the BF, and rotated the ring. Mark corrected the procedure.
Line 18: Line 15:
 * Type B Past Week Summary
  * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka.
  * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets.
  * Hirata-san worked on organizing:
   * Work platforms
   * Load gauge adapter and associated parts
   * Possible fall-back plans for the rods connecting the security structure to the PI.
==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Cable, test SF LVDT and FR.
 * Add calculated ballast to SF.
 * Finish tuning F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Move F0 #1 to "factory" area (in front of SRM) and start rebuild.

==== Plan for week of 6/18 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
 * --
 * Install PI.
 * Suspend SF/... section.
 * Lots of cabling.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo and Mark debugged the BS BIO connections and finally got it working. There were a total of four issues identified:
    • A wrong block used in the BS real-time model.
    • The real-time model deciding to treat the cards as numbered backwards from the slot order or the jumper settings.
    • Two unlabeled cables that may have been swapped.
    • The GAS coil driver and associated cables had been labeled HPCD #1 whereas it had been #0 in the diagram.
  • Hirata-san and Kozu-kun received the final F0 blades, characterized 6 of them and, with help from Takahashi-san, installed a matched set of 3 into PI #3. It appears to be 6 kg short of the load capacity that was targeted, but still with 4 kg of margin. It is close to having a good frequency but needs another round of tuning.
  • Mark and Terrence fixed an issue with the security structure - due to a screenshot of the CAD not updated from the BS procedure to the SR one, the BF ring had been placed 180° off in yaw. We suspended the BF from the load gauge adapter, reconfigured the BF jacks to support the ring instead of the BF, and rotated the ring. Mark corrected the procedure.

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Cable, test SF LVDT and FR.
  • Add calculated ballast to SF.
  • Finish tuning F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Move F0 #1 to "factory" area (in front of SRM) and start rebuild.

Plan for week of 6/18

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
  • --
  • Install PI.
  • Suspend SF/... section.
  • Lots of cabling.