 * Type B Past Week Summary
  * Flags and metal prisms ordered; expected 5/31.
  * New assembly drawing [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5179| D1605179]] focussing on items not part of main chain (and associated screws):
   * Crane adapter
   * Lower breadboard blade module (with cable clamps)
   * IM-RM safety bar ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5127| D1605127]] from last week now obsolete)
  * 3D assembly changed to have geophones instead of accelerometers (but SRx will probably be per original design - need to revisit circuit diagram)
  * Concept for load gauge adapter decided (reuse crane adapter plate and jacks from below PI; add Misumi crossbars, cleanroom-compatible chain hoist: [[attachment: Crane Frame.pdf]])
  * Concept for second floor of clean booth decided (remove all floor panels; add bridge panels at right angles: [[attachment:BS Cleanbooth.pdf]])
  * Modified drawings for main assembly frame and drawings for most small parts (jack adapters etc) received from Mirapro.
  * Wire sizes decided: 300 µm piano wire and 500 µm tungsten (will revisit this later).
  * Lots of work on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4817| E1604817]] (Fabian; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!191&authkey=!AMe0pdcd9GDm1H0&ithint=folder%2cwebloc|Draft on OneDrive]]) and [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]] (Mark; [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder%2cwebloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Report for week of 10/15 ====
===== SRM =====
 * We received the fourth feedthrough we had been waiting for and installed it on the AF.
 * Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
 * Fabian and Enzo connected up the Sat Amps.
 * Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
 * Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.
 * Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
 * Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
 * We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
 * Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
 * Enzo made a new batch of feedthrough adapters.
===== SR2 =====
 * We finalized the geophone cabling and reinstalled the geophones.
 * We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
 * Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.
==== Plan for week of 10/22 ====
 * Friday is NAOJ Open Day Prep - no Kamioka work.
 * Mark, Hirata-san and Fabian at Kamioka Mon-Thu.
 * Enzo at Kamioka Tue-Thu.
===== SR2 =====
 * Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
 * Continue shakedown.
 * Gather parts for the OL (with help from Simon).
===== SRM =====
 * Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
 * Suspend/weigh/balance the BF/... section.
 * Build up the AF and SS to the SF level.
 * Install the SF.
==== Plan for week of 10/29 ====
 * Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.
===== SR2 =====
 * Set up OL.
===== SRM =====
 * Continue assembly.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 18: Line 46:
 * Type B Past Week Summary
  * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka.
  * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets.
  * Hirata-san worked on organizing:
   * Work platforms
   * Load gauge adapter and associated parts
   * Possible fall-back plans for the rods connecting the security structure to the PI.
==== Vacation/Visitor Info ====
 * Terrence: 10/29-11/2 at Kamioka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/15

SRM
  • We received the fourth feedthrough we had been waiting for and installed it on the AF.
  • Fabian added the cables between the FE computer and the ADC/DAC boxes, and we checked that we were getting IO in the real-time model.
  • Fabian and Enzo connected up the Sat Amps.
  • Fabian double-checked the optic pitch, got the IRM nicely aligned to the IM, cabled IM OSEMs V1, V2, V3 and H1, and adjusted those OSEMs in/out to midrange.
  • Hirata-san set the compression on the F0 to 30 mm and measured the height and frequency as a function of load. He then fixed a loose screw on one of the blade tips and repeated the measurement. The frequency was fairly constant at around 0.5, which will do. He did a mass budget and chose a F1 CuBe spring. We may do a tiny bit more compression if the frequency degrades, and/or choose an even stronger spring if the load capacity is not enough.

  • Hirata-san took apart and reassembled one of the LBB blade units, which had a badly seated blade.
  • Hirata-san put cable clamps on the SF and on the PI. We are very short on the PEEK clamp pieces, so he scavenged some from SR2.
  • We added a new LAN hub for SRM, and configured two stepper drivers as SRM_IP and SRM_GAS.
  • Late in the week we received extra Type 3-4 cables (thanks to Sato-san for expediting) and were able to cable IM OSEMs H2 and H3, and the BF LVDT.
  • Enzo made a new batch of feedthrough adapters.

SR2
  • We finalized the geophone cabling and reinstalled the geophones.
  • We received the new arc weights, and used some of them to install a basic allotment of 6 38-mm weights on SR3 per the CAD. We then added two extra 19-mm arc weights for tuning and got a good IP frequency of 0.133 Hz.
  • Apart from the F0 yaw stepper issue and the OL, the SR2 is now more-or-less complete and adjusted mechanically, and just needs software work (control loops etc). We will however have to borrow one of the geophones at some point to do a huddle test with the final batch of new geophones (including those for SRM). Terrence can set up the OL in the week of 10/29.

Plan for week of 10/22

  • Friday is NAOJ Open Day Prep - no Kamioka work.
  • Mark, Hirata-san and Fabian at Kamioka Mon-Thu.
  • Enzo at Kamioka Tue-Thu.

SR2
  • Do a measurement of how much torque is required on the F0 keystone to move the system in yaw. (This will help Sato-san choose a suitable stepper driver for the new design.)
  • Continue shakedown.
  • Gather parts for the OL (with help from Simon).

SRM
  • Scavenge HPCDs from SR2 and SR3 (currently we only have one for SRM) and organize to get LPCDs modified.
  • Suspend/weigh/balance the BF/... section.
  • Build up the AF and SS to the SF level.
  • Install the SF.

Plan for week of 10/29

  • Mark, Enzo, Hirata-san, Fabian and Terrence at Kamioka Mon-Fri.

SR2
  • Set up OL.

SRM
  • Continue assembly.

To-Do Lists, Schedule