==== Past week report ====
At Kamioka (Mark, Enzo, Simon, Type Bp team):
 * Mark remade the BF pico adapter cable which was poorly made and had also been damaged.
 * The Type Bp team tided up the BS rack and made new labels for many cables (thanks!).
 * Enzo connected up the in-air cables for the picos and steppers.
 * Mark and Enzo renumbered the PI LVDTs, geophones and LVDTs to make a consistent scheme working anticlockwise.
 * Enzo and Mark debugged all the cables. The only problem we couldn't solve was that the actuator coil for PI LVDT #0 is open-circuit at the connector on the LVDT. (It has been intermittent but worked before the craning.) We may have to redo the connector or replace the LVDT. Limited TFs will be possible in the next week.
 * Simon set up the LSOL and was easily able to get a return beam from the mirror on the dummy BS.
 * Shoda-san copied over the LSOL section of the PR3 real-time model into the BS model and made other improvements (thanks!).
 * Mark brought home
==== Report for week of 1/29 ====
 * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
 * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
 * Fabian installed ballast masses in the BF.
 * Mark worked on schedule.
 * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Line 17: Line 13:
At Mitaka (Fabian, Hirata-san):
 * Fabian finished designing final trim masses for IM/BF/SF for the final hang of the BS and passed it to Hirata-san to make drawings and get quotes.
 * Hirata-san requested quotes for the replaceable-jaw version of the BS wire clamps.
 * Fabian and Hirata-san gathered needed items for the BS prism/flag gluing.
 * Hirata-san designed receptacles for the new rods with 8 mm heads and requested quotes.
==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)
 * Enzo on vacation
 * Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Line 23: Line 24:
==== Plan for week of 7/3 ====
 * Do prism/flag gluing on real BS at Kashiwa (whole team).
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).
==== Plan for week of 7/10 ====
 Mark and Enzo at Kamioka:
 * Fix broken LVDT actuator coil.
 * Test picos and steppers more fully.
==== Plan for week of 2/19 ====
 * Enzo back from Tuesday.
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.

==== Plan for week of 2/26 ====
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.

==== Vacation Info ====
 * Enzo 1/30-2/19.
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
  • Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
  • Fabian installed ballast masses in the BF.
  • Mark worked on schedule.
  • Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)
  • Enzo on vacation
  • Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

Plan for week of 2/19

  • Enzo back from Tuesday.
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

Plan for week of 2/26

  • Add Cu segments to SF cap.
  • Lift SF/... section and check total mass and balance.

Vacation Info

  • Enzo 1/30-2/19.
  • Fabian 4/2-4/27 vacation (then gone).