Line 7: Line 7:
At Kamioka (Mark, Enzo, Simon, Type Bp team):
 * Mark remade the BF pico adapter cable which was poorly made and had also been damaged.
 * The Type Bp team tided up the BS rack and made new labels for many cables (thanks!).
 * Enzo connected up the in-air cables for the picos and steppers.
 * Mark and Enzo renumbered the PI LVDTs, geophones and LVDTs to make a consistent scheme working anticlockwise.
 * Enzo and Mark debugged all the cables. The only problem we couldn't solve was that the actuator coil for PI LVDT #0 is open-circuit at the connector on the LVDT. (It has been intermittent but worked before the craning.) We may have to redo the connector or replace the LVDT. Limited TFs will be possible in the next week.
 * Simon set up the LSOL and was easily able to get a return beam from the mirror on the dummy BS.
 * Shoda-san copied over the LSOL section of the PR3 real-time model into the BS model and made other improvements (thanks!).
 * Mark brought home
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We characterized the remachined LBB blades, chose three and installed them in the LBB blade units in the PI.
 * We removed all sticky labels from the PI and cleaned the affected areas (and as much as possible of the rest of the surface) with ethanol.
 * We rearranged the arc weights on the PI to make space for the magic wand and installed the magic wand.
 * We rearranged the magnets on the SF damper ring to suit three Cu segments (instead of two as in the test hang).
 * We put proper vacuum-compatible tubing around all the stepper motor connections on the top of the PI (replacing cling wrap).
 * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
 * We closed the BF, craned the SF back in, and hooked the BF/..., this time with the hex cable clamp.
 * We routed cables from the BF via the hex cable clamp to the SF level.
 * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
 * We adjusted all the IRM OSEMs laterally and in/out.
 * We calibrated the SF LVDT and tested the SF FR stepper.
 * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we had to lift it with slings and could not accurately trim it for pitch/roll.
 * Therefore we brought forward the craning in of the PI with the SF damper ring hanging from it.
 * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right considering the hex cable clamp and cables.
 * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
Line 17: Line 24:
At Mitaka (Fabian, Hirata-san):
 * Fabian finished designing final trim masses for IM/BF/SF for the final hang of the BS and passed it to Hirata-san to make drawings and get quotes.
 * Hirata-san requested quotes for the replaceable-jaw version of the BS wire clamps.
 * Fabian and Hirata-san gathered needed items for the BS prism/flag gluing.
 * Hirata-san designed receptacles for the new rods with 8 mm heads and requested quotes.
==== Plan for week of 9/13 ====
Mark (except Wed), Fabian (except Mon, Tue), Enzo, Ohishi-san (except Mon-Wed), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Reinstall F0-SF rod, this time with hex cable clamp.
 * Route cables.
 * Adjust SF trim mass, adjust tilt and vertical.
 * Adjust SF damper gap.
 * Cable and test IP LVDTs.
 * Cable and test F0 LVDT.
 * Cable and test PI steppers.
 * Cable and test geophones.
 *
==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<BR>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Install LBB damper rings.
 * Install suspension.
Line 23: Line 41:
==== Plan for week of 7/3 ====
 * Do prism/flag gluing on real BS at Kashiwa (whole team).
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).

==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
 * Fix broken LVDT actuator coil.
 * Learn how Miyo-kun's pico driver software works and make improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
Fabian and Hirata-san at Mitaka.
 * Design SR assembly frame.
 * Inventory for SR.
==== Vacation Info ====
Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We characterized the remachined LBB blades, chose three and installed them in the LBB blade units in the PI.
  • We removed all sticky labels from the PI and cleaned the affected areas (and as much as possible of the rest of the surface) with ethanol.
  • We rearranged the arc weights on the PI to make space for the magic wand and installed the magic wand.
  • We rearranged the magnets on the SF damper ring to suit three Cu segments (instead of two as in the test hang).
  • We put proper vacuum-compatible tubing around all the stepper motor connections on the top of the PI (replacing cling wrap).
  • We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
  • We closed the BF, craned the SF back in, and hooked the BF/..., this time with the hex cable clamp.
  • We routed cables from the BF via the hex cable clamp to the SF level.
  • We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
  • We adjusted all the IRM OSEMs laterally and in/out.
  • We calibrated the SF LVDT and tested the SF FR stepper.
  • We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we had to lift it with slings and could not accurately trim it for pitch/roll.
  • Therefore we brought forward the craning in of the PI with the SF damper ring hanging from it.
  • We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right considering the hex cable clamp and cables.
  • However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.

Plan for week of 9/13

Mark (except Wed), Fabian (except Mon, Tue), Enzo, Ohishi-san (except Mon-Wed), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Reinstall F0-SF rod, this time with hex cable clamp.
  • Route cables.
  • Adjust SF trim mass, adjust tilt and vertical.
  • Adjust SF damper gap.
  • Cable and test IP LVDTs.
  • Cable and test F0 LVDT.
  • Cable and test PI steppers.
  • Cable and test geophones.

Plan for week of 9/19

No work Mon 9/18 (敬老の日)<BR> Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Install LBB damper rings.
  • Install suspension.

Vacation Info

Mark: 10/16-24