Line 7: Line 7:
At Kamioka (Mark, Enzo, Simon, Type Bp team):
 * Mark remade the BF pico adapter cable which was poorly made and had also been damaged.
 * The Type Bp team tided up the BS rack and made new labels for many cables (thanks!).
 * Enzo connected up the in-air cables for the picos and steppers.
 * Mark and Enzo renumbered the PI LVDTs, geophones and LVDTs to make a consistent scheme working anticlockwise.
 * Enzo and Mark debugged all the cables. The only problem we couldn't solve was that the actuator coil for PI LVDT #0 is open-circuit at the connector on the LVDT. (It has been intermittent but worked before the craning.) We may have to redo the connector or replace the LVDT. Limited TFs will be possible in the next week.
 * Simon set up the LSOL and was easily able to get a return beam from the mirror on the dummy BS.
 * Shoda-san copied over the LSOL section of the PR3 real-time model into the BS model and made other improvements (thanks!).
 * Mark brought home
 * Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
 * Enzo and Mark did a new overview screen for the BS.
 * Enzo added DIO cards to the rack and connected them to the coil drivers.
 * Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
 * Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
 * Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.
Line 17: Line 14:
At Mitaka (Fabian, Hirata-san):
 * Fabian finished designing final trim masses for IM/BF/SF for the final hang of the BS and passed it to Hirata-san to make drawings and get quotes.
 * Hirata-san requested quotes for the replaceable-jaw version of the BS wire clamps.
 * Fabian and Hirata-san gathered needed items for the BS prism/flag gluing.
 * Hirata-san designed receptacles for the new rods with 8 mm heads and requested quotes.
Line 23: Line 15:
==== Plan for week of 7/3 ====
 * Do prism/flag gluing on real BS at Kashiwa (whole team).
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).
==== Plan for week of 12/25 ====
 * Power outage 12/25.
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
 * Recover after power outage.
 * Create SR2 real-time model.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * Weigh IM (per Fabian's note in the paper log).
 * Remove L-brackets from bars on IM ring - send for cleaning/remachining.
 * Setup OL for checking pitch of SR.
 * Wipe/blow dust off SR2 frame.
 * Crane IM into frame.
Line 34: Line 28:
==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
 * Fix broken LVDT actuator coil.
 * Learn how Miyo-kun's pico driver software works and make improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
Fabian and Hirata-san at Mitaka.
 * Design SR assembly frame.
 * Inventory for SR.
==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
  • Enzo and Mark did a new overview screen for the BS.
  • Enzo added DIO cards to the rack and connected them to the coil drivers.
  • Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
  • Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
  • Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.

Plan for week of 12/25

  • Power outage 12/25.
  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
  • Recover after power outage.
  • Create SR2 real-time model.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • Weigh IM (per Fabian's note in the paper log).
  • Remove L-brackets from bars on IM ring - send for cleaning/remachining.
  • Setup OL for checking pitch of SR.
  • Wipe/blow dust off SR2 frame.
  • Crane IM into frame.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5