Differences between revisions 163 and 213 (spanning 50 versions)
Revision 163 as of 2017-07-07 09:59:19
Size: 3066
Editor: MarkBarton
Comment:
Revision 213 as of 2017-12-22 09:59:50
Size: 1622
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).
 * Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
 * Enzo and Mark did a new overview screen for the BS.
 * Enzo added DIO cards to the rack and connected them to the coil drivers.
 * Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
 * Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
 * Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.
Line 12: Line 14:
At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.
Line 24: Line 15:
==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Test picos and steppers more fully.
 * Finish tidying rack and labeling cables.
 
==== Plan for week of 12/25 ====
 * Power outage 12/25.
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
 * Recover after power outage.
 * Create SR2 real-time model.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * Weigh IM (per Fabian's note in the paper log).
 * Remove L-brackets from bars on IM ring - send for cleaning/remachining.
 * Setup OL for checking pitch of SR.
 * Wipe/blow dust off SR2 frame.
 * Crane IM into frame.

==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
Line 33: Line 37:
Fabian, Hirata-san at Mitaka.
 * Do new 3D CAD (Hirata-san):
  * SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Fabian/Mark to do.)
  * Final BS build, SS/PI/SF as for Test Hang but with BF/IRM/IM/BS/RM down rotated back to original direction.
   * On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
   * In-tank version.
 * Solve arc weight versus magic wand problem.
 * Do mass budget for LBB - design ballast masses (Fabian)
 * Run TFs, make improvements to real-time model (Mark, Enzo).
 * Design SR assembly frame.
 * Inventory for SR.
==== Plan for week of 7/10 ====
Mark and Enzo at Kamioka:
Fabian and Hirata-san at Mitaka.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
  • Enzo and Mark did a new overview screen for the BS.
  • Enzo added DIO cards to the rack and connected them to the coil drivers.
  • Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
  • Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
  • Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.

Plan for week of 12/25

  • Power outage 12/25.
  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
  • Recover after power outage.
  • Create SR2 real-time model.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • Weigh IM (per Fabian's note in the paper log).
  • Remove L-brackets from bars on IM ring - send for cleaning/remachining.
  • Setup OL for checking pitch of SR.
  • Wipe/blow dust off SR2 frame.
  • Crane IM into frame.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)