At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
 * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
 * We pulled out all the old in-air cabling.
 * We laid about 9 new in-air cables.
 * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
 * We connected up, tested and calibrated the BF LVDT.
 * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
At Mitaka (Hirata-san:
 * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
 * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
 * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
 * He liaised with Koshin-shoko about modification of BS LBB blade springs.
 * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
 * He worked on the 3D model of SR3 SUS wires, and making a list for quotation.
Line 12: Line 23:
At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.
==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Internship: Kozu-kun (Mon-Fri)<<BR>>
Line 24: Line 27:
==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Document LVDT driver rebuild and other changes.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Design/install matrices, blend filters and damping filters.
 * Finish tidying rack and labeling cables.
 * Add temporary ballast to LBB and find total required.
 * Try rearranging arc weights to make room for magic wand.
 * Start on creating SR3 rack.
 * Preparation for BF rebuild.
 
Fabian, Hirata-san at Mitaka.
 * Clean BS secondary prisms and modified gluing jigs (Hirata-san).
 * Ship gluing tools and BS to Kamioka.
 * Do new 3D CAD for final BS install (Hirata-san):
  * On-assembly-frame version.
  * In-tank version.
 * Design SR assembly frame (Fabian).
 * Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
 * Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
 * Do mass budget for LBB - design ballast masses (Fabian)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
 * Swap in new IM ballast masses; readjust height and levelness.
 * Install side panels of IRM and OSEMs.
 * Route IRM OSEM cables, test/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Try TFs with optical sensors.
Mitaka: Hirata-san.
 * SR stuff.
Line 48: Line 38:
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
==== Plan for week of 8/28 ====
Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
 *

==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):

  • We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
  • We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
  • We pulled out all the old in-air cabling.
  • We laid about 9 new in-air cables.
  • We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
  • We connected up, tested and calibrated the BF LVDT.
  • We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.

At Mitaka (Hirata-san:

  • Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
  • He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
  • He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
  • He liaised with Koshin-shoko about modification of BS LBB blade springs.
  • He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
  • He worked on the 3D model of SR3 SUS wires, and making a list for quotation.

Plan for week of 8/21

Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)

Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).

  • Swap in new IM ballast masses; readjust height and levelness.
  • Install side panels of IRM and OSEMs.
  • Route IRM OSEM cables, test/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Try TFs with optical sensors.

Mitaka: Hirata-san.

  • SR stuff.

Plan for week of 8/28

Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.

Vacation Info

Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct