Line 7: Line 7:
At Kamioka (Enzo):
 * Enzo (with help from Miyo-kun) fixed the broken actuation coil on PI LVDT #0.
 * Enzo worked on the final cabling plan for BS and SRx.
 * Enzo replaced the LVDT driver again to have one with no dead channels (and free up the partly non-working cards for servicing).
Line 12: Line 8:
At Mitaka and Kashiwa (Mark, Hirata-san, Fabian, Enzo):
 * We glued magnets into their holders.
 * We did a walk-through of the gluing procedure at Mitaka and discovered that the secondary prisms were missing.
 * We took the mirror box and gluing tools to Kashiwa to do as much of the gluing as possible.
 * Hirose-san applied First Contact to the BS and he and Kieran moved it into the mirror box.
 * We practiced putting sapphire prisms on the BS but didn't apply glue.
 * We tried the magnet gluing jigs designed by Aso-san and found two major issues: the overall length was about 25 mm too long, and there was no adjustment to allow for the wedge.
 * We designed a simple modification to the jigs that hopefully would be trivial for the ATC to do: the jigs will be cut in half and the bottom section will be mounted with adhesive on an 11 mm rod that slides in the central hole of the top section. Thus the top half can be screwed into the existing recess, and the bottom half with the magnets and glue can be allowed to drop about 3 mm onto the face of the optic. Hirata-san worked with ATC to get this done and it should be ready today (Friday 7/7).
 * Hirata-san also got ATC to make some jigs to hold the old 5-mm prisms so that they can be ground down to 3 mm to replace the missing ones. Hirata-san will do the grinding himself today (Friday 7/7/).
 * We decided to continue the gluing work at Kamioka, so we brought the BS back to Mitaka and will ship it on to Kamioka next Tuesday.
 * Hirata-san did a version of the 3D CAD with the as-built BS Test Hang configuration.
 * Mark finished the OL calibration/diagonalization calculation and wrote it up as klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3835|3835]] and [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7205| T1707205-v4]].
 * We glued the prisms and magnets on the SR2.
 * We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
 * We weighed the BF for the SR2.
 * Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
 * Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
 * Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
 * Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
 * Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
 * Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
 * Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
 * Shoda-san created a BS Guardian.
 * We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.
Line 24: Line 22:
==== Plan for weeks of 7/10, 7/17 ====
Mark, Enzo mostly at Kamioka.
 * More TFs.
 * Receive BS at Kamioka, do gluing if possible.
 * Document LVDT driver rebuild and other changes.
 * Learn how Miyo-kun's pico driver software works and make fixes/improvements.
 * Design/install matrices, blend filters and damping filters.
 * Finish tidying rack and labeling cables.
 * Add temporary ballast to LBB and find total required.
 * Try rearranging arc weights to make room for magic wand.
 * Start on creating SR3 rack.
 * Preparation for BF rebuild.
 
Fabian, Hirata-san at Mitaka.
 * Clean BS secondary prisms and modified gluing jigs (Hirata-san).
 * Ship gluing tools and BS to Kamioka.
 * Do new 3D CAD for final BS install (Hirata-san):
  * On-assembly-frame version.
  * In-tank version.
 * Design SR assembly frame (Fabian).
 * Do 2D Drawings and procurement of final IM/BF/SF ballast masses (Hirata-san).
 * Other purchasing and preparation (spare BS clamps, suspension wire, 8-mm rod receptacles)
 * Do mass budget for LBB - design ballast masses (Fabian)
==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
 * Find plumb bob.
 * Assembly frame alignment and optical table centering. (Mark and Hirata)
 * Finish IM assembly and pico test. (Fabian and Enzo)
 * Do inventory of ballast masses. (Fabian)
Line 48: Line 30:
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
==== Plan for week of 12/25 ====
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
 * Install IM ring interface blocks and IM ring.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * OL setup.

==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark finished the OL calibration/diagonalization calculation and wrote it up as klog 3835 and T1707205-v4.

  • We glued the prisms and magnets on the SR2.
  • We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
  • We weighed the BF for the SR2.
  • Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
  • Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
  • Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
  • Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
  • Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
  • Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
  • Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
  • Shoda-san created a BS Guardian.
  • We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
  • Find plumb bob.
  • Assembly frame alignment and optical table centering. (Mark and Hirata)
  • Finish IM assembly and pico test. (Fabian and Enzo)
  • Do inventory of ballast masses. (Fabian)

Plan for week of 12/25

  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
  • Install IM ring interface blocks and IM ring.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • OL setup.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21