Differences between revisions 166 and 180 (spanning 14 versions)
Revision 166 as of 2017-07-14 13:32:20
Size: 2280
Editor: MarkBarton
Comment:
Revision 180 as of 2017-08-25 13:48:16
Size: 1874
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Enzo, Yoshioka-kun):
 * We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
 * We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
 * We put the blocks back under the LBB and unhooked it.
 * We moved the suspension from the tank back to the assembly frame.
 * We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
 * We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
 * We checked the centering of the security frame in the assembly frame and disconnected it from the PI. One M12x35 screw galled after a few turns and will need attention.
 * Enzo started setting up the SR3 rack (with help from Yamamoto-san).
 * We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
 * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
 * We checked the range of the BF FR.
 * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
 * We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
 * We set up the optical sensors facing the RM.
 * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
 * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
 * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
 * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
 * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
 * Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
 * Hirata-san did several cost-reduction negotiations with Mirapro.
Line 18: Line 22:
At Mitaka (Fabian and Hirata-san):
 * Hirata-san shipped the optic and gluing tools to Kamioka.
 * Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
 * Fabian worked on the SRx assembly frame.
Line 23: Line 23:
==== Plan for week of 7/18 ====
Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).
 * Glue prisms/magnets on BS.
 * Dismantle suspension.
 * Finish setting up filter service area (mostly already done by Mirapro).
 * Move BF to filter service area, start rebuild.
==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.
Line 30: Line 31:
==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Finish BF rebuild.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.
==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
Line 36: Line 36:
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):

  • We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
  • We checked the range of the BF FR.
  • We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
  • We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
  • We set up the optical sensors facing the RM.
  • We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
  • We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
  • We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
  • We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
  • We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.

At Mitaka (Hirata-san):

  • Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
  • Hirata-san did several cost-reduction negotiations with Mirapro.

Plan for week of 8/28

Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).

  • Fix/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Suspend BF/IRM/IM/RM/BS.

Plan for week of 9/4

  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.

Vacation Info

Mark: TBD Mid-Oct

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)