Differences between revisions 166 and 209 (spanning 43 versions)
Revision 166 as of 2017-07-14 13:32:20
Size: 2280
Editor: MarkBarton
Comment:
Revision 209 as of 2017-12-01 13:33:12
Size: 1857
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Enzo, Yoshioka-kun):
 * We experimented with rearranging the arc weights to accommodate the magic wands and came up with a suitable scheme.
 * We used spare arc weights as extra ballast on the LBB to get it to float, and measured the height for a known load.
 * We put the blocks back under the LBB and unhooked it.
 * We moved the suspension from the tank back to the assembly frame.
 * We craned the LBB rings down onto the LBB but did not remove them yet. (This however is the last crane work in the tank until reinstallation, so the lid does not have to come off again and the pallet can be used for the PI.)
 * We put the crossbars back in the assembly frame underneath the SF and BF (and corrected an error in the height of the BF ones).
 * We checked the centering of the security frame in the assembly frame and disconnected it from the PI. One M12x35 screw galled after a few turns and will need attention.
 * Enzo started setting up the SR3 rack (with help from Yamamoto-san).
 * We received the real BS optic and gluing tools, and glued the disks and rods into the modified magnet jigs. We also tried the re-made secondary prisms in the gluing jigs and made shims to hold them more securely.
Line 18: Line 8:
At Mitaka (Fabian and Hirata-san):
 * Hirata-san shipped the optic and gluing tools to Kamioka.
 * Hirata-san did drawings and RFQs for IM/BF/SF ballast masses
 * Fabian worked on the SRx assembly frame.
 * We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
 * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
 * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
 * Enzo found nearly all in-vacuum cables.
 * Enzo and Shoda-san got several more loops closed on the BS.
 * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
 * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
 * Hirata-san worked on SR procurement.
 * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
 
==== Plan for week of 12/4 ====
 * Mark at Kamioka.
 * Fabian at f2f satellite meeting Mon, then Kamioka.
 * Enzo at f2f then Mitaka.
 * Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
 * Kozu-kun Thu only.
 * Mirror gluing.
 * IM assembly and pico test.
Line 23: Line 27:
==== Plan for week of 7/18 ====
Full team at Kamioka from Tue-Fri, except Hirata-san (Tue-Wed only).
 * Glue prisms/magnets on BS.
 * Dismantle suspension.
 * Finish setting up filter service area (mostly already done by Mirapro).
 * Move BF to filter service area, start rebuild.
==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
 * Kozu-kun Mon-Thu only.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.
Line 30: Line 34:
==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Finish BF rebuild.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.
==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Line 36: Line 38:
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo TBD, probably 12/22-1/3
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
  • Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
  • Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
  • Enzo found nearly all in-vacuum cables.
  • Enzo and Shoda-san got several more loops closed on the BS.
  • Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
  • Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
  • Hirata-san worked on SR procurement.
  • Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.

Plan for week of 12/4

  • Mark at Kamioka.
  • Fabian at f2f satellite meeting Mon, then Kamioka.
  • Enzo at f2f then Mitaka.
  • Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
  • Kozu-kun Thu only.
  • Mirror gluing.
  • IM assembly and pico test.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
  • Kozu-kun Mon-Thu only.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo TBD, probably 12/22-1/3
  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)