At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. |
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables. * We hung the RM and set its pitch. * We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system. * We installed the bottom section of the security structure to protect the RM/BS. * We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses. * We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame. * We brought in the new BF. * We installed the BF-IRM rods and IRM top plate. * We reinstalled the IM flags and other items that had been taken off to use the winch system. * We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.) * We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT). |
Line 16: | Line 20: |
==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish disassembly. * Finish BF rebuild. * Remove LBB rings. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. |
==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).<<BR>> * Remove LBB blade units from PI, then remove blades and send for remachining. * Remove LBB rings from chamber and send for recleaning. * Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical. * Test, calibrate BF LVDT. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR Stuff |
Line 25: | Line 31: |
==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. |
Line 31: | Line 36: |
Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We finished installing the RM OSEMs and installed the new Type5-2.2 and 5-2.4 OSEM cables.
- We hung the RM and set its pitch.
- We doubled-checked the BS and RM pitch, tightened the clamps and removed the winch system.
- We installed the bottom section of the security structure to protect the RM/BS.
- We lifted the IM/RM/BS section and weighed it. It was about 1.25 kg too heavy for the new BF, so we improvised a lighter set of ballast masses.
- We installed the section of the security structure up to the BF ring, and the BF crossbars and jacks of the assembly frame.
- We brought in the new BF.
- We installed the BF-IRM rods and IRM top plate.
- We reinstalled the IM flags and other items that had been taken off to use the winch system.
- We hooked the BF-IM rod (with hex cable clamp). (We did not unlock the BF keystone.)
- We cabled and tested the IM-PIT, IM-ROL and IM-YAW picos and the BF FR stepper (but not, yet, the BF LVDT).
Plan for week of 8/14
Site closure: Mon, Tue
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (Thu-Fri).
- Remove LBB blade units from PI, then remove blades and send for remachining.
- Remove LBB rings from chamber and send for recleaning.
- Unlock BF, adjust ballast masses on IM/RM/BS to correct pitch/roll/vertical.
- Test, calibrate BF LVDT.
Mitaka: Hirata-san (Mon-Fri)
- SR Stuff
Plan for week of 8/21
Vacation: Fabian (Mon)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
Vacation Info: Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct