Line 7: | Line 7: |
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. |
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece. * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework. * We pulled out all the old in-air cabling. * We laid about 9 new in-air cables. * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon. * We connected up, tested and calibrated the BF LVDT. * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday. |
Line 16: | Line 16: |
==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish disassembly. * Finish BF rebuild. * Remove LBB rings. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> |
Line 25: | Line 20: |
==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. |
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; tweak height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. |
Line 30: | Line 31: |
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 |
==== Plan for week of 8/28 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; tweak height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. ==== Vacation Info ==== |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
- We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
- We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
- We pulled out all the old in-air cabling.
- We laid about 9 new in-air cables.
- We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
- We connected up, tested and calibrated the BF LVDT.
- We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
Plan for week of 8/21
Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
- Swap in new IM ballast masses; tweak height and levelness.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Try TFs with optical sensors.
Mitaka: Hirata-san.
- SR stuff.
Plan for week of 8/28
Vacation: Fabian (Mon)
Internship: Kozu-kun (Mon-Fri)
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
- Swap in new IM ballast masses; tweak height and levelness.
- Install side panels of IRM and OSEMs.
- Route IRM OSEM cables, test/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Try TFs with optical sensors.
Mitaka: Hirata-san.
- SR stuff.
Vacation Info
Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct