==== Past week report ==== At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun): * We lubricated the stuck screw at the top of the security structure with stuck and were able to remove it. * Enzo disconnected and removed or coiled many in-vac cables at the PI level to free it. * We craned the PI. There was a minor safety incident - see below. * Hirata-san set up the filter service area, and we moved in a BF intended for one of the SRs (BF#3). * Fabian and Hirata-san worked out a method for characterizing a single spring, and Fabian finished characterizing the first one. * We did a big tidy-up and clean-up of the area, especially the corner where we intended to do the gluing. * We set up the BS gluing jigs and applied the glue. We will check the results on Monday. |
==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]). * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods. * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 2/5 ==== * Enzo on vacation; all others at Kamioka. * - * Make in-air pico adapter cables. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. |
Line 16: | Line 27: |
==== Plan for week of 7/24 ==== Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation). * Check results of gluing. * Finish disassembly. * Finish BF rebuild. * Remove LBB rings. * Recheck alignment of assembly frame and centering of optical table. * Install IM, suspend BS and RM. |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日)<<BR>> * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * All others at Kamioka. * - * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. |
Line 25: | Line 36: |
==== Plan for week of 7/31 ==== Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation). * Weigh/trim BS/RM/IM. * Bring in rebuilt BF. |
==== Plan for week of 2/19 ==== * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Add Cu segments to SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
Line 30: | Line 46: |
Vacation Info: Hirata-san: Thu 7/20 through Mon 7/24 Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30). * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).
We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).
- We referred the BS OL.
We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog 4073).
- Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
- Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
- Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
- Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- -
- Make in-air pico adapter cables.
- Calibrate LVDT.
- Test IM picos and BF yaw pico.
- Test FR.
- Install ballast mass in BF.
- Build IRM around IM.
Plan for week of 2/13
No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
- All others at Kamioka.
- -
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Add Cu segments to SF cap.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30).