Differences between revisions 169 and 224 (spanning 55 versions)
Revision 169 as of 2017-07-28 13:55:30
Size: 2688
Editor: MarkBarton
Comment:
Revision 224 as of 2018-02-02 09:34:57
Size: 2165
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Past week report ====
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We disassembled the suspension.
  * We removed all the cables and bagged and labelled them for reuse.
  * The PI is parked on the pallet.
  * The SF was initially parked between the frame and tank and then manhandled to one side. The same procedure was used for the SF ring.
  * The BF was parked between the assembly frame and tank. The BF ring was stored in the top of the structure.
  * We removed various useful and no-longer-needed items from the BF, including the lower rod receptacle, thrust bearing, fishing rod and temporary ballast masses.
  * We cut the wires and removed the RM and dummy BS on the RM trolley.
 * The wire clamps were moderately deeply scarred and could probably be reused, but we plan to use the new set, which will be available on Tuesday of next week.
 * We discovered that the problem with the old BF was due to the fishing rod, which had not had a pair of lock nuts and had been damaged by being drive too high, so that the springs hit the underside of the cap and were bent at the base. We will install lock nuts and set them to the correct height for the final installation.
 * The gluing of the BS primary prisms and magnets went well, but we had to reglue the secondary prisms because they stuck to the jigs and were pulled off when the jigs were retracted. The second try went well and the BS is ready for use.
 * Fabian and Hirata-san characterized 7 new BS BF blades. There was one outlier but the rest were in a tight group.
 * Hirata-san used 3 of the blades to build a new BF.
 * Miyo-kun and others from the Type Bp team did a lot of tidying up of the BS rack for us, and removed a lot of in-air cables running through the cleanbooth. When he returns, on 8/8, Enzo will coordinate relaying the cables in the cable trays (which were not installed when the initial cabling was done).
==== Report for week of 1/29 ====
 * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
 * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]).
 * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]).
 * We referred the BS OL.
 * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
 * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
 * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
 * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
 * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
 
Line 22: Line 18:
==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Make in-air pico adapter cables.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Calibrate LVDT.
 * Get screws for ballast mass from Takahashi-san.
 * Install ballast mass in BF.
 * Set up for F0 test.
  * Lower IM crossbars in SR3 assembly frame.
  * Open curtain on SR3 crane slot.
  * Set up dummy load (weight carrier, rods etc).
 * Do F0 test.
  * Bring in F0.
  * Hook up dummy load.
  * Adjust dummy load.
Line 23: Line 37:
==== Plan for week of 7/24 ====
Full team at Kamioka from Mon-Fri, except Hirata-san (Tue-Fri) and Enzo (vacation).
 * Check results of gluing.
 * Finish disassembly.
 * Finish BF rebuild.
 * Remove LBB rings.
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.
==== Plan for week of 2/5 ====
 * Enzo on vacation; all others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Line 32: Line 43:
==== Plan for week of 7/31 ====
Full team at Kamioka from Mon-Fri, except Fabian (Mon-Thu) and Enzo (vacation).
 * Weigh/trim BS/RM/IM.
 * Bring in rebuilt BF.
==== Plan for week of 2/12 ====
 * Enzo on vacation; all others at Kamioka.
Line 37: Line 46:
Vacation Info:
Hirata-san: Thu 7/20 through Mon 7/24
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
==== Vacation Info ====
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
  • Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).

  • We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).

  • We referred the BS OL.
  • We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
  • Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
  • Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
  • Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
  • Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Make in-air pico adapter cables.
  • Test IM picos and BF yaw pico.
  • Test FR.
  • Calibrate LVDT.
  • Get screws for ballast mass from Takahashi-san.
  • Install ballast mass in BF.
  • Set up for F0 test.
    • Lower IM crossbars in SR3 assembly frame.
    • Open curtain on SR3 crane slot.
    • Set up dummy load (weight carrier, rods etc).
  • Do F0 test.
    • Bring in F0.
    • Hook up dummy load.
    • Adjust dummy load.

Plan for week of 2/5

  • Enzo on vacation; all others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Plan for week of 2/12

  • Enzo on vacation; all others at Kamioka.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)