Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka.
  * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets.
  * Hirata-san worked on organizing:
   * Checking Mirapro assembly frame drawings
   * Ordering missing screws and small items (screws for dummy mass, fine pitch M8 for RM)
   * Work platforms and clean booth second floor arrangement.
   * Load gauge adapter and associated parts
   * Possible fall-back plans for the rods connecting the security structure to the PI.
   * Design for additional trim masses (existing design had no provision for adding/removing).
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
 * Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
 * Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
 * Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
 * We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
 * We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
 * We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.

==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 6/6:
 * Cabling:
  * Finish moving in-air cabling to match feedthrough positions.
  * Cable and test PI vertical LVDT.
  * Calibrate PI vertical LVDT.
  * Set yoke on PI vertical LVDT (if necessary).
  * Cable and test PI yaw stepper.
  * Cable and test PI vertical stepper.
  * Cable and test PI horizontal steppers.
  * Cable and test PI horizontal LVDTs.
  * Calibrate PI horizontal LVDTs.

Week of 6/12:
 * Remove -Y flange cover, replace with cloth cover (or foil).
 * Prepare LBB.
  * Wipe LBB.
  * Loosen or remove LBB hold-down bolts.
  * Attach LBB outriggers and rod receptacles.
  * Lay out slings for LBB damper rings.
 * Prepare LBB damper support.
  * Install rods for LBB magnet ring.
  * Install safety rods for LBB Cu ring.
 * Prepare LBB Cu ring.
  * Pass into tank.
  * Reassemble on top of slings.
  * Lay down spacers to protect magnets (in next step).
 * Prepare LBB magnet ring.
  * Assemble temporarily.
  * Attach magnets with template.
  * Disassemble.
  * Pass into tank.
  * Reassemble on top of Cu ring.
 * Install LBB damper.
  * Pass sling ends through loops to bind LBB damper rings.
  * Remove vacuum tank lid and ring.
  * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
 * Crane suspension into tank.
 * Hook LBB Cu ring.
 * Hook LBB.
 * Crane vacuum tank lid+ring black on.
 * Remove vacuum tank lid (only).
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Cabling, cabling, cabling.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Hirata-san):

  • Hirata-san and Mark reversed the support ring for the LBB damper to match the reversed suspension.
  • Hirata-san did a trial assembly of the magnet ring for the LLB damper and placed magnets on it with the template.
  • Hirata-san and Mark put the base pieces for the Cu ring in the chamber. However it turns out that the holes for attaching the joint pieces are incompletely threaded and we will have to run a tap through them.
  • We tested the geophones. At first one didn't work at all. This turned out to be a broken wire in one of the in-vacuum adapter cables. For the test we replaced the adapter with an old-style one (and removed the matching descrambler). A second geophone mostly works but saturates at a suspiciously low number of counts at the ADC (2000 instead of 20000).
  • We tested the PI horizontal LVDTs. The #1 (H2) one works but cable swaps showed that #0 and #2 have issues both at the tank end and at the card.
  • We decided on a final location for the stepper and pico drivers on the second floor. We moved the cables for the stepper drivers (using the outside cable trays) and laid new LAN and AC cables for the picos.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 6/6:

  • Cabling:
    • Finish moving in-air cabling to match feedthrough positions.
    • Cable and test PI vertical LVDT.
    • Calibrate PI vertical LVDT.
    • Set yoke on PI vertical LVDT (if necessary).
    • Cable and test PI yaw stepper.
    • Cable and test PI vertical stepper.
    • Cable and test PI horizontal steppers.
    • Cable and test PI horizontal LVDTs.
    • Calibrate PI horizontal LVDTs.

Week of 6/12:

  • Remove -Y flange cover, replace with cloth cover (or foil).
  • Prepare LBB.
    • Wipe LBB.
    • Loosen or remove LBB hold-down bolts.
    • Attach LBB outriggers and rod receptacles.
    • Lay out slings for LBB damper rings.
  • Prepare LBB damper support.
    • Install rods for LBB magnet ring.
    • Install safety rods for LBB Cu ring.
  • Prepare LBB Cu ring.
    • Pass into tank.
    • Reassemble on top of slings.
    • Lay down spacers to protect magnets (in next step).
  • Prepare LBB magnet ring.
    • Assemble temporarily.
    • Attach magnets with template.
    • Disassemble.
    • Pass into tank.
    • Reassemble on top of Cu ring.
  • Install LBB damper.
    • Pass sling ends through loops to bind LBB damper rings.
    • Remove vacuum tank lid and ring.
    • Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
  • Crane suspension into tank.
  • Hook LBB Cu ring.
  • Hook LBB.
  • Crane vacuum tank lid+ring black on.
  • Remove vacuum tank lid (only).
  • Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
  • Cabling, cabling, cabling.