* Type B Past Week Summary * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka. * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets. * Hirata-san worked on organizing: * Checking Mirapro assembly frame drawings * Ordering missing screws and small items (screws for dummy mass, fine pitch M8 for RM) * Work platforms and clean booth second floor arrangement. * Load gauge adapter and associated parts * Possible fall-back plans for the rods connecting the security structure to the PI. * Design for additional trim masses (existing design had no provision for adding/removing). |
=== Type B (Mark) === ==== Report for week of 5/28 ==== * Enzo tested the LVDT driver repaired by Tanaka-san - it was fine. * Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data. * Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF. * Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings). * After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole. * Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2). * Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3). * Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades. * We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles. * We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap. * Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank. * Enzo installed damping filters for the IM OSEMs. ==== Plan for week of 5/28 ==== * Mark, Enzo at Kamioka Mon-Fri. * Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.) * Matteo at Kamioka from Tue. He may help Type B to get experience. * Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.) * -- ==== Plan for week of 6/4 ==== * Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.) * -- * Cable and test BF cap picos. * Build up security structure to SF level. * Crane in SF and remove cap. * Hook BF and adjust total ballast. * Route cables through SF-BF flying saucer up to bottom of SF. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Add budgeted ballast mass to SF and weigh SF/... section. * Cable, test SF LVDT and FR. * Characterize final F0 blades. ==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Rebuild F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Make LBB blade sets (or at least 3 of 9). ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 5/28
- Enzo tested the LVDT driver repaired by Tanaka-san - it was fine.
- Fujii-kun and Enzo finished assembling a batch of 4 geophones and took test data.
- Hirata-san modified some Promec masses (drilling out the threads on 2 of 4 holes) so we could use two layers of them inside the BF.
- Hirata-san installed maraging rod receptacles in the LBB damper rings, and in the bottom of PIs #3 and #1 (for the SF damper rings).
- After consulting with various people, Hirata-san installed the second half of the LBB top ring in the chamber, simply omitting the pillar and screw associated with the badly threaded hole.
- Hirata-san took delivery of the screws for the LBB blade units, made up 9 blade units and installed 6 of them on PI #3 and #1 (for SR3 and SR2).
- Hirata-san made up a set of PI cable clamps and installed them on PI #3 (for SR3).
- Hirata-san removed the prototype blades from PI #3 to get ready for testing the final blades.
- We located the #355 disk and #356 poles for the next level of the security structure up to the SF and installed the poles.
- We installed ballast mass in the BF. After some trial and error we settled on 16 Promec masses (7.1 kg) inside the BF and 5 D1808104-4 and 3 D1808104-5 masses (540 g) on the cap.
- Enzo and Fujii-kun did several rounds of TFs on the BF/... section of the suspension and debugged a problem with dewhitening filters not being installed in the OSEMINF filter bank.
- Enzo installed damping filters for the IM OSEMs.
Plan for week of 5/28
- Mark, Enzo at Kamioka Mon-Fri.
- Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
- Matteo at Kamioka from Tue. He may help Type B to get experience.
- Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
- --
Plan for week of 6/4
- Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
- --
- Cable and test BF cap picos.
- Build up security structure to SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF and weigh SF/... section.
- Cable, test SF LVDT and FR.
- Characterize final F0 blades.
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Make LBB blade sets (or at least 3 of 9).