* Type B Past Week Summary * Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka. * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets. * Hirata-san worked on organizing: * Checking Mirapro assembly frame drawings * Ordering missing screws and small items (screws for dummy mass, fine pitch M8 for RM) * Work platforms and clean booth second floor arrangement. * Load gauge adapter and associated parts * Possible fall-back plans for the rods connecting the security structure to the PI. * Design for additional trim masses (existing design had no provision for adding/removing). |
=== Type B (Mark) === ==== Report for week of 7/30 ==== * ==== Plan for week of 8/6 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Do TFs with temporary OL. * Install final OL. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). ===== SR2 ===== * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Assemble metal mass. * Glue prisms, flags. * Reconfigure, align assembly frame. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/30
Plan for week of 8/6
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Do TFs with temporary OL.
- Install final OL.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
SR2
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Assemble metal mass.
- Glue prisms, flags.
- Reconfigure, align assembly frame.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.
To-Do Lists, Schedule
Vacation Info
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.