Size: 954
Comment:
|
Size: 1044
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
* Fabian did inventory of parts/fasteners for dummy BS, RM, IM and IRM - almost all at Mitaka. A handful (picos, pico drivers) will be brought back from Kamioka. * Fabian continued work on Mathematica and Matlab models of the BS and control system. He now gets much better agreement after correcting discrepancies between the parameter sets. * Hirata-san worked on organizing: * Checking Mirapro assembly frame drawings * Ordering missing screws and small items (screws for dummy mass, fine pitch M8 for RM) * Work platforms and clean booth second floor arrangement. * Load gauge adapter and associated parts * Possible fall-back plans for the rods connecting the security structure to the PI. * Design for additional trim masses (existing design had no provision for adding/removing). |
* Mark and Hirata-san at Mitaka * Gathered parts for cable making. * Mark and Hirata-san at Kamioka: * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame. * Installed two more LPCDs and the stepper motor driver in the PR2 rack. * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs). * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs. * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement. * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4). * Added extension to the IM pico cable for the BF yaw pico. * Made LVDT adapter cable. * Mark worked on schedule. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark and Hirata-san at Mitaka
- Gathered parts for cable making.
- Mark and Hirata-san at Kamioka:
- Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
- Installed two more LPCDs and the stepper motor driver in the PR2 rack.
- Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
- Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
- Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
- Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
- Added extension to the IM pico cable for the BF yaw pico.
- Made LVDT adapter cable.
- Mark worked on schedule.
- Mark and Hirata-san at Mitaka