Line 7: Line 7:
At Kamioka (Mark, Enzo, Hirata-san, Yoshioka-kun):
 * We disassembled the suspension.
  * We removed all the cables and bagged and labelled them for reuse.
  * The PI is parked on the pallet.
  * The SF was initially parked between the frame and tank and then manhandled to one side. The same procedure was used for the SF ring.
  * The BF was parked between the assembly frame and tank. The BF ring was stored in the top of the structure.
  * We removed various useful and no-longer-needed items from the BF, including the lower rod receptacle, thrust bearing, fishing rod and temporary ballast masses.
  * We cut the wires and removed the RM and dummy BS on the RM trolley.
 * The wire clamps were moderately deeply scarred and could probably be reused, but we plan to use the new set, which will be available on Tuesday of next week.
 * We discovered that the problem with the old BF was due to the fishing rod, which had not had a pair of lock nuts and had been damaged by being drive too high, so that the springs hit the underside of the cap and were bent at the base. We will install lock nuts and set them to the correct height for the final installation.
 * The gluing of the BS primary prisms and magnets went well, but we had to reglue the secondary prisms because they stuck to the jigs and were pulled off when the jigs were retracted. The second try went well and the BS is ready for use.
 * Fabian and Hirata-san characterized 7 new BS BF blades. There was one outlier but the rest were in a tight group.
 * Hirata-san used 3 of the new blades to build a new BF.
 * Miyo-kun and others from the Type Bp team did a lot of tidying up of the BS rack for us, and removed a lot of in-air cables running through the cleanbooth. When he returns, on 8/8, Enzo will coordinate relaying the cables in the cable trays (which were not installed when the initial cabling was done).
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
 * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
 * We checked the range of the BF FR.
 * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
 * We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
 * We set up the optical sensors facing the RM.
 * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
 * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
 * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
 * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
 * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
 * Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
 * Hirata-san did several cost-reduction negotiations with Mirapro.
Line 23: Line 23:
==== Plan for week of 7/31 ====
Kamioka: Mark (Mon-Fri), Fabian (Mon-Wed), Hirata-san (Tue-Thu), Yoshioka-kun (Tue, Wed, Fri) <<BR>>
Mitaka: Hirata-san (Mon, Fri)<<BR>>
Enzo: vacation
 * Recheck alignment of assembly frame and centering of optical table.
 * Install IM, suspend BS and RM.
 * Remove LBB rings (time permitting).
==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.
Line 31: Line 31:
==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).
Mitaka: Hirata-san (Mon-Fri)
Vacation: Enzo (Mon), Fabian (Thu, Fri)
 * Weigh/trim BS/RM/IM.
 * Take out old BF; bring in rebuilt BF.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.
==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
Line 41: Line 36:
Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
==== Vacation Info ====

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):

  • We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
  • We checked the range of the BF FR.
  • We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
  • We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
  • We set up the optical sensors facing the RM.
  • We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
  • We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
  • We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
  • We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
  • We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.

At Mitaka (Hirata-san):

  • Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
  • Hirata-san did several cost-reduction negotiations with Mirapro.

Plan for week of 8/28

Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).

  • Fix/adjust IRM OSEMs.
  • Add BF cap; cable and test BF-1 and BF-2 picos.
  • Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
  • Crane in SF.
  • Suspend BF/IRM/IM/RM/BS.

Plan for week of 9/4

  • Install SF cap; route cables.
  • Lift and weigh SF/BF/IRM/IM/RM/BS.
  • Adjust SF ballast.

Vacation Info