==== Past week report ==== At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun): * We reconfigured the top of the assembly frame. * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces. * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys. * We re-installed, centered and leveled the IM. * We solved two issues with the new wire clamps: * Some holes were not properly threaded - Hirata-san retapped them. * Some locating pins were loose - we glued them. * We mounted the BS mirror box on the trolley and brought it under the IM. * We installed the winch system and the 300 µm wires for the BS. * We set up the optical lever. * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in. |
==== Past two weeks report ==== Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 20: | Line 16: |
==== Plan for week of 8/7 ==== Site closure: Friday<<BR>> Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>> * Finish hanging BS * Hang RM. * Weigh/trim BS/RM/IM. * Suspend BS/RM/IM, add IRM. * Lay new in-air OSEM cables. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR stuff. |
Mitaka (Fabian, Hirata-san): * Fabian did mechanical design: * F0 FR * Cable clamps for the SR IP base. * New SR recoil ballast masses. * LBB ballast. * Update of BS 3D CAD with the as-built ballast. * Hirata-san * made and updated inventory list for SR. * made order list and asked some quotes. * Ordered some parts. * Talked with mirapro about SRM optical bench. * Made some drawings for SR preparation. |
Line 32: | Line 30: |
==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>> Mitaka: Hirata-san (Mon-Fri)<<BR>> |
==== Plan for week of 11/13 ==== |
Line 38: | Line 32: |
Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Enzo and Kozu-kun at Mitaka * Servos * Diagonalization of OL * TFs of BF * Documentation Mark and Fabian at Kamioka. * Mark attends commissioning workshop at U Toyama. * Support BF characterization work. * Prepare for mirror gluing. * Prepare for IM assembly. Hirata-san at Mitaka * SR procurement. * Get BS prism-gluing jigs reworked for use with PR/SR mirror box. ==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Fabian did mechanical design:
- F0 FR
- Cable clamps for the SR IP base.
- New SR recoil ballast masses.
- LBB ballast.
- Update of BS 3D CAD with the as-built ballast.
- Hirata-san
- made and updated inventory list for SR.
- made order list and asked some quotes.
- Ordered some parts.
- Talked with mirapro about SRM optical bench.
- Made some drawings for SR preparation.
Plan for week of 11/13
Enzo and Kozu-kun at Mitaka
- Servos
- Diagonalization of OL
- TFs of BF
- Documentation
Mark and Fabian at Kamioka.
- Mark attends commissioning workshop at U Toyama.
- Support BF characterization work.
- Prepare for mirror gluing.
- Prepare for IM assembly.
Hirata-san at Mitaka
- SR procurement.
- Get BS prism-gluing jigs reworked for use with PR/SR mirror box.
Plan for week of 11/20
- Holiday on Thu 3/23
- Fabian at commissioning workshop