1708
Comment:
|
1857
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun): * We reconfigured the top of the assembly frame. * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces. * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys. * We re-installed, centered and leveled the IM. * We solved two issues with the new wire clamps: * Some holes were not properly threaded - Hirata-san retapped them. * Some locating pins were loose - we glued them. * We mounted the BS mirror box on the trolley and brought it under the IM. * We installed the winch system and the 300 µm wires for the BS. * We set up the optical lever. * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in. |
|
Line 20: | Line 8: |
==== Plan for week of 8/7 ==== Site closure: Friday<<BR>> Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>> * Finish hanging BS * Hang RM. * Weigh/trim BS/RM/IM. * Suspend BS/RM/IM, add IRM. * Lay new in-air OSEM cables. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR stuff. |
* We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box. * Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.) * Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.) * Enzo found nearly all in-vacuum cables. * Enzo and Shoda-san got several more loops closed on the BS. * Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4). * Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them. * Hirata-san worked on SR procurement. * Hirata-san worked with Mirapro to get the SRM LBB installed in the tank. ==== Plan for week of 12/4 ==== * Mark at Kamioka. * Fabian at f2f satellite meeting Mon, then Kamioka. * Enzo at f2f then Mitaka. * Hirata-san at Kamioka Mon-Thu, Mitaka Fri. * Kozu-kun Thu only. * Mirror gluing. * IM assembly and pico test. |
Line 32: | Line 27: |
==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>> Mitaka: Hirata-san (Mon-Fri)<<BR>> |
==== Plan for week of 12/11 * Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka. * Kozu-kun Mon-Thu only. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. |
Line 38: | Line 34: |
Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. ==== Vacation Info ==== * Mark 12/22-1/3 * Enzo TBD, probably 12/22-1/3 * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- We brought the SR2 optic into the tunnel and moved it into the good mirror box. The spare mirror was moved into the not-so-good mirror box.
- Enzo assembled the SR2 rack and laid all the long cables from the rack into the cleanbooth. (Hayakawa-san can now proceed with the rebuilding of the changing cleanbooth.)
- Mark and Shoda-san took data for calibrating and diagonalizing the OL. (Due to the odd angle of the first steering mirror, the beam pattern is rotated by 62° at the QPD.)
- Enzo found nearly all in-vacuum cables.
- Enzo and Shoda-san got several more loops closed on the BS.
- Mark found three geophone pods and two feedthrough adapters for SR2 (now have 3 FAs but need 4).
- Mark took out S-numbers for anonymous boxes in the SR2 and put yellow stickers supplied by Tomura-san on them.
- Hirata-san worked on SR procurement.
- Hirata-san worked with Mirapro to get the SRM LBB installed in the tank.
Plan for week of 12/4
- Mark at Kamioka.
- Fabian at f2f satellite meeting Mon, then Kamioka.
- Enzo at f2f then Mitaka.
- Hirata-san at Kamioka Mon-Thu, Mitaka Fri.
- Kozu-kun Thu only.
- Mirror gluing.
- IM assembly and pico test.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Hirata-san, Shoda-san at Kamioka.
- Kozu-kun Mon-Thu only.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
- Enzo TBD, probably 12/22-1/3
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21