At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun): * We reconfigured the top of the assembly frame. * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces. * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys. * We re-installed, centered and leveled the IM. * We solved two issues with the new wire clamps: * Some holes were not properly threaded - Hirata-san retapped them. * Some locating pins were loose - we glued them. * We mounted the BS mirror box on the trolley and brought it under the IM. * We installed the winch system and the 300 µm wires for the BS. * We set up the optical lever. * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in. * We suspended the BS and set its height and pitch. |
|
Line 21: | Line 8: |
==== Plan for week of 8/7 ==== Site closure: Friday<<BR>> Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>> Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>> * Adjust RM OSEMs; add new RM cable clamp piece. * Hang RM. * Run new (longer) OSEM cables. * Weigh/trim BS/RM/IM. * Suspend BS/RM/IM, add IRM. * Lay new in-air OSEM cables. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR stuff. |
* Mark worked on SR2 planning. * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436). * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out. * Hirata-san ordered more disks for IM flags. * Hirata-san asked for quotes on SF LBB blades. * Hirata-san got a reduced quote for the LBB damper rings. * Hirata-san received and cleaned suspension wires for the SR. * Fabian worked on the SR mass budget. * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions. * Enzo and Kozu-kun worked on control filter design and installation. |
Line 34: | Line 19: |
==== Plan for week of 8/14 ==== Site closure: Mon, Tue<<BR>> Vacation: Fabian (Mon-Fri) Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>> * Bring in BF and hang BS/RM/IM/IRM. Mitaka: Hirata-san (Mon-Fri)<<BR>> * SR Stuff? Vacation Info: Enzo: Sat 7/22 through Sun 8/6 Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
==== Plan for week of 11/27 ==== * Fabian at commissioning workshop * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation. * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly. * Mark from Mon lunchtime. * Kozu-kun from Mon lunchtime through Wed. * Mirror gluing. * SR2 rack setup. ==== Plan for week of 12/4 ==== * All at Kamioka * IM assembly and pico test. * Assembly frame alignment and optical table centering. * OL setup. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark worked on SR2 planning.
- Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
- Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
- Hirata-san ordered more disks for IM flags.
- Hirata-san asked for quotes on SF LBB blades.
- Hirata-san got a reduced quote for the LBB damper rings.
- Hirata-san received and cleaned suspension wires for the SR.
- Fabian worked on the SR mass budget.
- Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
- Enzo and Kozu-kun worked on control filter design and installation.
Plan for week of 11/27
- Fabian at commissioning workshop
- Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
- All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
- Mark from Mon lunchtime.
- Kozu-kun from Mon lunchtime through Wed.
- Mirror gluing.
- SR2 rack setup.
Plan for week of 12/4
- All at Kamioka
- IM assembly and pico test.
- Assembly frame alignment and optical table centering.
- OL setup.