At Kamioka (Mark, Fabian, Hirata-san, Yoshioka-kun):
 * We reconfigured the top of the assembly frame.
 * We cleaned the assembly frame, blowing dust out of the grooves and wiping all surfaces.
 * We recentered the optic table in the bottom of the frame and adjusted the frame until the top was centered over the optic table. We also recentered the trolleys.
 * We re-installed, centered and leveled the IM.
 * We solved two issues with the new wire clamps:
  * Some holes were not properly threaded - Hirata-san retapped them.
  * Some locating pins were loose - we glued them.
 * We mounted the BS mirror box on the trolley and brought it under the IM.
 * We installed the winch system and the 300 µm wires for the BS.
 * We set up the optical lever.
 * Hirata-san finished the new BF. We moved the old BF out of the cleanbooth and the new one in.
 * We suspended the BS and set its height and pitch.
Line 21: Line 8:
==== Plan for week of 8/7 ====
Site closure: Friday<<BR>>
Vacation: Enzo (Mon), Fabian (Mon-Fri)<<BR>>
Kamioka: Mark (Mon-Thu), Enzo (Tue-Thu), Yoshioka-kun (Tue, Wed), Ohishi (TBD).<<BR>>
 * Adjust RM OSEMs; add new RM cable clamp piece.
 * Hang RM.
 * Run new (longer) OSEM cables.
 * Weigh/trim BS/RM/IM.
 * Suspend BS/RM/IM, add IRM.
 * Lay new in-air OSEM cables.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR stuff.
 * Mark finished the OL calibration/diagonalization calculation and wrote it up as klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3835|3835]] and [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7205| T1707205-v4]].
 * We glued the prisms and magnets on the SR2.
 * We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
 * We weighed the BF for the SR2.
 * Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
 * Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
 * Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
 * Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
 * Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
 * Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
 * Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
 * Shoda-san created a BS Guardian.
 * We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.
Line 34: Line 22:
==== Plan for week of 8/14 ====
Site closure: Mon, Tue<<BR>>
Vacation: Fabian (Mon-Fri)
Kamioka: Mark (Wed-Fri), Enzo (Wed-Fri), Yoshioka-kun (Wed, Fri), Ohishi (TBD).<<BR>>
 * Bring in BF and hang BS/RM/IM/IRM.
Mitaka: Hirata-san (Mon-Fri)<<BR>>
 * SR Stuff?
Vacation Info:
Enzo: Sat 7/22 through Sun 8/6
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
 * Find plumb bob.
 * Assembly frame alignment and optical table centering. (Mark and Hirata)
 * Finish IM assembly and pico test. (Fabian and Enzo)
 * Do inventory of ballast masses. (Fabian)

==== Plan for week of 12/25 ====
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
 * Install IM ring interface blocks and IM ring.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * OL setup.

==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark finished the OL calibration/diagonalization calculation and wrote it up as klog 3835 and T1707205-v4.

  • We glued the prisms and magnets on the SR2.
  • We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
  • We weighed the BF for the SR2.
  • Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
  • Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
  • Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
  • Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
  • Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
  • Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
  • Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
  • Shoda-san created a BS Guardian.
  • We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
  • Find plumb bob.
  • Assembly frame alignment and optical table centering. (Mark and Hirata)
  • Finish IM assembly and pico test. (Fabian and Enzo)
  • Do inventory of ballast masses. (Fabian)

Plan for week of 12/25

  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
  • Install IM ring interface blocks and IM ring.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • OL setup.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21