Differences between revisions 177 and 214 (spanning 37 versions)
Revision 177 as of 2017-08-18 11:08:37
Size: 2427
Editor: MarkBarton
Comment:
Revision 214 as of 2018-01-04 13:48:34
Size: 1557
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
 * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
 * We pulled out all the old in-air cabling.
 * We laid about 9 new in-air cables.
 * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
 * We connected up, tested and calibrated the BF LVDT.
 * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
 * Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
 * Enzo and Mark did a new overview screen for the BS.
 * Enzo added DIO cards to the rack and connected them to the coil drivers.
 * Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
 * Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
 * Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.
Line 16: Line 14:
==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Internship: Kozu-kun (Mon-Fri)<<BR>>
Line 20: Line 15:
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
 * Swap in new IM ballast masses; tweak height and levelness.
 * Install side panels of IRM and OSEMs.
 * Route IRM OSEM cables, test/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Try TFs with optical sensors.
Mitaka: Hirata-san.
 * SR stuff.
==== Plan for week of 12/25 ====
 * Power outage 12/25.
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
 * Recover after power outage.
 * Create SR2 real-time model.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * Weigh IM (per Fabian's note in the paper log).
 * Remove L-brackets from bars on IM ring - send for cleaning/remachining.
 * Setup OL for checking pitch of SR.
 * Wipe/blow dust off SR2 frame.
 * Crane IM into frame.
Line 31: Line 28:
==== Plan for week of 8/28 ====
Vacation: Fabian (Mon)<<BR>>
Internship: Kozu-kun (Mon-Fri)<<BR>>

Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
 * Swap in new IM ballast masses; tweak height and levelness.
 * Install side panels of IRM and OSEMs.
 * Route IRM OSEM cables, test/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Try TFs with optical sensors.
Mitaka: Hirata-san.
 * SR stuff.
==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.
Line 47: Line 33:
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
 * Enzo 1/30-2/19

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen.
  • Enzo and Mark did a new overview screen for the BS.
  • Enzo added DIO cards to the rack and connected them to the coil drivers.
  • Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range.
  • Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring.
  • Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime.

Plan for week of 12/25

  • Power outage 12/25.
  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD.
  • Recover after power outage.
  • Create SR2 real-time model.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • Weigh IM (per Fabian's note in the paper log).
  • Remove L-brackets from bars on IM ring - send for cleaning/remachining.
  • Setup OL for checking pitch of SR.
  • Wipe/blow dust off SR2 frame.
  • Crane IM into frame.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)