==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece. * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework. * We pulled out all the old in-air cabling. * We laid about 9 new in-air cables. * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon. * We connected up, tested and calibrated the BF LVDT. * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday. At Mitaka (Hirata-san: * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost. * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far). * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation. * He liaised with Koshin-shoko about modification of BS LBB blade springs. * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing. * He worked on the 3D model of SR3 SUS wires, and making a list for quotation. |
==== Past two weeks report ==== At Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 23: | Line 16: |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> |
Mitaka (Fabian, Hirata-san): * Hirata-san published his inventory of SR parts on Dropbox. |
Line 27: | Line 19: |
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; readjust height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. |
==== Plan for week of 11/13 ==== |
Line 38: | Line 21: |
==== Plan for week of 8/28 ==== Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * |
Kamioka: Mark * Attend commissioning workshop at U Toyama. * Be person-on-site for BF work. * Set up for mirror gluing. |
Line 42: | Line 26: |
==== Vacation Info ==== Fabian: Fri 8/4 through Mon 8/21 Mark: TBD Mid-Oct |
Mitaka: Fabian and Hirata-san * SR procurement. * New PI GAS FR design. * BS LBB ballast mass design. * SR cable lamp design. Mitaka: Enzo and Kozu-kun (Wed, Thu) * Servos * TFs of BF * Documentation |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
At Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Hirata-san published his inventory of SR parts on Dropbox.
Plan for week of 11/13
Kamioka: Mark
- Attend commissioning workshop at U Toyama.
- Be person-on-site for BF work.
- Set up for mirror gluing.
Mitaka: Fabian and Hirata-san
- SR procurement.
- New PI GAS FR design.
- BS LBB ballast mass design.
- SR cable lamp design.
Mitaka: Enzo and Kozu-kun (Wed, Thu)
- Servos
- TFs of BF
- Documentation