At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun): * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece. * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework. * We pulled out all the old in-air cabling. * We laid about 9 new in-air cables. * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon. * We connected up, tested and calibrated the BF LVDT. * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday. At Mitaka (Hirata-san: * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost. * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far). * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation. * He liaised with Koshin-shoko about modification of BS LBB blade springs. * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing. * He worked on the 3D model of SR3 SUS wires, and making a list for quotation. |
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs. * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IM |
Line 23: | Line 13: |
==== Plan for week of 8/21 ==== Vacation: Fabian (Mon)<<BR>> Internship: Kozu-kun (Mon-Fri)<<BR>> Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri). * Swap in new IM ballast masses; readjust height and levelness. * Install side panels of IRM and OSEMs. * Route IRM OSEM cables, test/adjust IRM OSEMs. |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. |
Line 34: | Line 19: |
* (Time permitting) Try TFs with optical sensors. Mitaka: Hirata-san. * SR stuff. |
* Suspend BF/IRM/IM/RM/BS. |
Line 38: | Line 21: |
==== Plan for week of 8/28 ==== Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun. * Suspend BF/IRM/IM/RM/BS. |
==== Plan for week of 9/4 ==== |
Line 46: | Line 27: |
Fabian: Fri 8/4 through Mon 8/21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs.
- We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
- We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
- We aligned the IM
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct