Differences between revisions 179 and 215 (spanning 36 versions)
Revision 179 as of 2017-08-18 13:24:57
Size: 2752
Editor: MarkBarton
Comment:
Revision 215 as of 2018-01-12 09:07:17
Size: 1822
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Past week report ====
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun, Kozu-kun):
 * We removed the LBB damper rings from the tank and passed them to Takahashi-san for recleaning. Unfortunately two screws galled, one holding on a Cu segment, and one holding on a joint piece.
 * We removed the LBB blade units from the PI, removed the blades and shipped them off for rework.
 * We pulled out all the old in-air cabling.
 * We laid about 9 new in-air cables.
 * We wrapped/labelled the BS mirror box, the winch system, the trolley adapters, and many other tools that we do not expect to use any time soon.
 * We connected up, tested and calibrated the BF LVDT.
 * We adjusted the ballast mass on the IM to make it hang level and at the right height. However we had to reduce the weight by a further 686 g relative to the plan of 2017-08-09. We found a combination that was good except for the fact that it used round masses on the bottom corners, so we decided to have the 641 g rectangular masses cut down by 60 g each. Mesco was able to do this within 24 hours. We will reclean the parts on Friday afternoon and swap them in on Monday.
At Mitaka (Hirata-san:
 * Hirata-san got a quotation about optical bench from Mirapro and contacted them about reducing cost.
 * He asked Suzuki-san (Tokyo university) to order them (delivery date is 10/24, so far).
 * He modified SR assembly frame design (from Fabian) and asked Mirapro for quotation.
 * He liaised with Koshin-shoko about modification of BS LBB blade springs.
 * He asked ATC for making t4.5 ballast mass for PR. He washed them and sent them to Kamioka with the PR thrust bearing.
 * He worked on the 3D model of SR3 SUS wires, and making a list for quotation.
==== Report for week of 12/25 ====
 * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
 * Shoda-san recovered the BS from the power outage on 12/25.
 * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
 * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
 * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
 * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
 * They ran cables for the SR2 steppers and OSEMs.
 * They calibrated the BF LVDT.
Line 23: Line 16:
==== Plan for week of 8/21 ====
Vacation: Fabian (Mon)<<BR>>
Internship: Kozu-kun (Mon-Fri)<<BR>>
==== Report for week of 1/4 ====
 * Mark fixed a number of errors with the Type B screens.
Line 27: Line 19:
Kamioka: Mark, Ohishi, Fabian (Tue-Fri), Enzo, Yoshioka-kun (Tue, Wed, Fri).
 * Swap in new IM ballast masses; readjust height and levelness.
 * Install side panels of IRM and OSEMs.
 * Route IRM OSEM cables, test/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * (Time permitting) Try TFs with optical sensors.
Mitaka: Hirata-san.
 * SR stuff.
==== Report for week of 1/9 ====
 * We weighed the mirror in its box (and later the empty box), and the RM.
 * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
 * We hung the SR2 and RM.
 * We assembled the bottom section of the security structure below the RM.
 * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
 * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.
Line 38: Line 27:
==== Plan for week of 8/28 ====
Kamioka: Mark, Ohishi, Fabian, Enzo, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun.
 * Suspend BF/IRM/IM/RM/BS.
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
==== Plan for week of 1/15 ====
 * Shoda-san at Mitaka making OSEMs.
 *
==== Plan for week of 1/22 ====

==== Plan for week of 1/22 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.
Line 46: Line 37:
Fabian: Fri 8/4 through Mon 8/21
Mark: TBD Mid-Oct
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/25

  • Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
  • Shoda-san recovered the BS from the power outage on 12/25.
  • Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
  • Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
  • They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
  • They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
  • They ran cables for the SR2 steppers and OSEMs.
  • They calibrated the BF LVDT.

Report for week of 1/4

  • Mark fixed a number of errors with the Type B screens.

Report for week of 1/9

  • We weighed the mirror in its box (and later the empty box), and the RM.
  • Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
  • We hung the SR2 and RM.
  • We assembled the bottom section of the security structure below the RM.
  • Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
  • Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.

Plan for week of 1/15

  • Shoda-san at Mitaka making OSEMs.

Plan for week of 1/22

Plan for week of 1/22

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2